A few key team members recently left the project team. The remaining members took time to understand the details and found it difficult to make progress. As a result, the project schedule is seriously delayed.

What should the project manager do?

A.
Request additional resources to be incorporated to the project team.
Answers
A.
Request additional resources to be incorporated to the project team.
B.
Observe the project team and give them time to catch up before escalating.
Answers
B.
Observe the project team and give them time to catch up before escalating.
C.
Escalate to the project sponsor and seek alternatives to resolve the issue.
Answers
C.
Escalate to the project sponsor and seek alternatives to resolve the issue.
D.
Review the issues and adjust the project plan to give a realistic schedule.
Answers
D.
Review the issues and adjust the project plan to give a realistic schedule.
Suggested answer: C