A project is in the middle of the fifth iteration. Due to a sudden slump in the economy, the company recorded a drastic reduction in revenue. The strategic direction was to Implement costreduction measures immediately.
What should the project manager do next?
A.
Continue the current sprint without interruption and address priorities in the upcoming product backlog grooming sessions.
B.
Meet with the sponsor for guidance on the best path forward before executing sprints.
C.
Allow the project team to decide on the best path forward for the current sprint.
D.
Schedule a meeting with the product owner, discuss priorities and decide if anything from the backlog can be eliminated, based on current constraints.