A project manager collects various pieces of information and consolidates metnics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.

What should the project manager do next?

A.
Add new members for the underperforming team
Answers
A.
Add new members for the underperforming team
B.
Seek an external expert to review the framework
Answers
B.
Seek an external expert to review the framework
C.
Arrange for external training amid the tight project schedules
Answers
C.
Arrange for external training amid the tight project schedules
D.
Foster knowledge sharing and coaching among team members
Answers
D.
Foster knowledge sharing and coaching among team members
Suggested answer: D