During project execution, one of the project tasks is to create an important document for a service vendor. The project manager assigns a senior engineer to clearly detail the service instructions to avoid any redo loops. Two days after the service information document was sent, the service vendor has doubts and needs more clarity on the task. This redo loop will probably cause a delay of one or more days.

What should the project manager do next?

Become a Premium Member for full access
  Unlock Premium Member

Question 1182

Report
Export
Collapse

During the execution phase of a project, one of the customer's stakeholders keeps requesting changes to the scope every week. Which three actions should the project manager take to resolve this issue? (Choose three.)

Become a Premium Member for full access
  Unlock Premium Member

Question 1183

Report
Export
Collapse

A project manager for an IT company starts a project with members distributed across five different countries and four different time zones. In the first meetings with the sponsor and some stakeholders, the project manager notices that people do not join the meetings on time, have internet connection issues, or experience language barriers during some conversations.

What should the project manager do to improve communication among the team?

Become a Premium Member for full access
  Unlock Premium Member

Question 1184

Report
Export
Collapse

A project manager is assigned midway through a project. The team members are in different locations across the country and they are unable to meet in-person often. During a status review meeting, one of the stakeholders highlighted that they were unaware of the status for the project deliverables.

What should the project manager do first?

Become a Premium Member for full access
  Unlock Premium Member

Question 1185

Report
Export
Collapse

A project that has to be delivered by the targeted date has been delayed due to an unforeseen risk occurrence. How should the project manager compress the project to ensure the completion date is not affected?

Become a Premium Member for full access
  Unlock Premium Member

Question 1186

Report
Export
Collapse

A client's company announces a reorganization, which includes changes in the senior management involved in the project. The new project sponsor is asking to put the project on hold until they review the scope.

What should the project manager do next?

Become a Premium Member for full access
  Unlock Premium Member

Question 1187

Report
Export
Collapse

A few key team members recently left the project team. The remaining members took time to understand the details and found it difficult to make progress. As a result, the project schedule is seriously delayed.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 1188

Report
Export
Collapse

A project is in the middle of the fifth iteration. Due to a sudden slump in the economy, the company recorded a drastic reduction in revenue. The strategic direction was to Implement costreduction measures immediately.

What should the project manager do next?

Become a Premium Member for full access
  Unlock Premium Member

Question 1189

Report
Export
Collapse

A project manager collects various pieces of information and consolidates metnics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.

What should the project manager do next?

Become a Premium Member for full access
  Unlock Premium Member

Question 1190

Report
Export
Collapse

A customer support team has planned short, iterative cycles for working on customer-reported issues. Recently, there was a surge of high-priority issues that disrupted the original plan, and the team's manager is finding it difficult to manage the progress.

Which approach should the project manager suggest using?