ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 1190 - PMP discussion

Report
Export

A customer support team has planned short, iterative cycles for working on customer-reported issues. Recently, there was a surge of high-priority issues that disrupted the original plan, and the team's manager is finding it difficult to manage the progress.

Which approach should the project manager suggest using?

A.
Agile Scrum approach
Answers
A.
Agile Scrum approach
B.
Agile Kanban approach
Answers
B.
Agile Kanban approach
C.
Spiral approach
Answers
C.
Spiral approach
D.
Rapid application development approach
Answers
D.
Rapid application development approach
Suggested answer: B
asked 23/09/2024
Matias Cordero Ochoa
35 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first