The product scope description is used to:

A.
Gain stakeholders' support for the project.
A.
Gain stakeholders' support for the project.
Answers
B.
Progressively elaborate the characteristics of the product, service, or result.
B.
Progressively elaborate the characteristics of the product, service, or result.
Answers
C.
Describe the project in great detail.
C.
Describe the project in great detail.
Answers
D.
Define the process and criteria for accepting a completed product, service, or result.
D.
Define the process and criteria for accepting a completed product, service, or result.
Answers
Suggested answer: B

Which technique is used in Perform Quantitative Risk Analysis?

A.
Sensitivity analysis
A.
Sensitivity analysis
Answers
B.
Probability and impact matrix
B.
Probability and impact matrix
Answers
C.
Risk data quality assessment
C.
Risk data quality assessment
Answers
D.
Risk categorization
D.
Risk categorization
Answers
Suggested answer: A

Which illustrates the connection between work that needs to be done and its project team members?

A.
Work breakdown structure (WBS)
A.
Work breakdown structure (WBS)
Answers
B.
Network diagrams
B.
Network diagrams
Answers
C.
Staffing management plan
C.
Staffing management plan
Answers
D.
Responsibility assignment matrix (RAM)
D.
Responsibility assignment matrix (RAM)
Answers
Suggested answer: D

Which tools or techniques will a project manager use for Develop Project Team?

A.
Negotiation
A.
Negotiation
Answers
B.
Roles and responsibilities
B.
Roles and responsibilities
Answers
C.
Recognition and rewards
C.
Recognition and rewards
Answers
D.
Prizing and promoting
D.
Prizing and promoting
Answers
Suggested answer: C

Which of the following is an input to Direct and Manage Project Execution?

A.
Requested changes
A.
Requested changes
Answers
B.
Approved change requests
B.
Approved change requests
Answers
C.
Work performance information
C.
Work performance information
Answers
D.
Implemented defect repair
D.
Implemented defect repair
Answers
Suggested answer: B

Which of the following is TRUE about most project life cycles?

A.
Staffing level is highest at the start.
A.
Staffing level is highest at the start.
Answers
B.
The stakeholders' influence is highest at the start.
B.
The stakeholders' influence is highest at the start.
Answers
C.
The level of uncertainty is lowest at the start.
C.
The level of uncertainty is lowest at the start.
Answers
D.
The cost of changes is highest at the start.
D.
The cost of changes is highest at the start.
Answers
Suggested answer: B

An input required in Define Scope is an organizational:

A.
structure.
A.
structure.
Answers
B.
process asset.
B.
process asset.
Answers
C.
matrix.
C.
matrix.
Answers
D.
breakdown structure.
D.
breakdown structure.
Answers
Suggested answer: B

What cost control technique is used to compare actual project performance to planned or expected performance?

A.
Cost aggregation
A.
Cost aggregation
Answers
B.
Trend analysis
B.
Trend analysis
Answers
C.
Forecasting
C.
Forecasting
Answers
D.
Variance analysis
D.
Variance analysis
Answers
Suggested answer: D

What is the term assigned to products or services having the same functional use but different technical characteristics?

A.
Scope
A.
Scope
Answers
B.
Quality
B.
Quality
Answers
C.
Specification
C.
Specification
Answers
D.
Grade
D.
Grade
Answers
Suggested answer: D

When is a Salience Model used?

A.
In a work breakdown structure (WBS)
A.
In a work breakdown structure (WBS)
Answers
B.
During quality assurance
B.
During quality assurance
Answers
C.
In stakeholder analysis
C.
In stakeholder analysis
Answers
D.
During quality control (QC)
D.
During quality control (QC)
Answers
Suggested answer: C