The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:

A.
Supportive
A.
Supportive
Answers
B.
Leading
B.
Leading
Answers
C.
Neutral
C.
Neutral
Answers
D.
Resistant
D.
Resistant
Answers
Suggested answer: B

Which of the following is a narrative description of products, services, or results to be delivered by a project?

A.
Project statement of work
A.
Project statement of work
Answers
B.
Business case
B.
Business case
Answers
C.
Accepted deliverable
C.
Accepted deliverable
Answers
D.
Work performance information
D.
Work performance information
Answers
Suggested answer: A

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

A.
Historical information and the lessons-learned database.
A.
Historical information and the lessons-learned database.
Answers
B.
Historical information and the stakeholder register.
B.
Historical information and the stakeholder register.
Answers
C.
Organizational process assets and the lessons-learned database.
C.
Organizational process assets and the lessons-learned database.
Answers
D.
Project documents and historical information.
D.
Project documents and historical information.
Answers
Suggested answer: A

Projects are undertaken by an organization to support the:

A.
Product performance.
A.
Product performance.
Answers
B.
Budget process.
B.
Budget process.
Answers
C.
Collective capabilities.
C.
Collective capabilities.
Answers
D.
Organizational strategy.
D.
Organizational strategy.
Answers
Suggested answer: D

What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?

A.
0.45
A.
0.45
Answers
B.
0.56
B.
0.56
Answers
C.
0.70
C.
0.70
Answers
D.
1.36
D.
1.36
Answers
Suggested answer: C

Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?

A.
Histograms
A.
Histograms
Answers
B.
Scatter diagrams
B.
Scatter diagrams
Answers
C.
Flowcharts
C.
Flowcharts
Answers
D.
Checksheets
D.
Checksheets
Answers
Suggested answer: D

The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:

A.
start-to-start (SS)
A.
start-to-start (SS)
Answers
B.
start-to-finish (SF)
B.
start-to-finish (SF)
Answers
C.
finish-to-start (FS)
C.
finish-to-start (FS)
Answers
D.
finish-to-finish (FF)
D.
finish-to-finish (FF)
Answers
Suggested answer: C

Work performance information and cost forecasts are outputs of which Project Cost Management process?

A.
Estimate Costs
A.
Estimate Costs
Answers
B.
Plan Cost Management
B.
Plan Cost Management
Answers
C.
Determine Budget
C.
Determine Budget
Answers
D.
Control Costs
D.
Control Costs
Answers
Suggested answer: D

Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?

A.
Coaching
A.
Coaching
Answers
B.
Avoidance
B.
Avoidance
Answers
C.
Consensus
C.
Consensus
Answers
D.
Influencing
D.
Influencing
Answers
Suggested answer: B

The procurement process that documents agreements and related documentation for future reference is known as:

A.
Plan Procurements.
A.
Plan Procurements.
Answers
B.
Control Procurements.
B.
Control Procurements.
Answers
C.
Close Procurements.
C.
Close Procurements.
Answers
D.
Conduct Procurements.
D.
Conduct Procurements.
Answers
Suggested answer: C