A collection of projects managed as a group to achieve strategic objectives is referred to as a:

A.
plan
A.
plan
Answers
B.
process
B.
process
Answers
C.
program
C.
program
Answers
D.
portfolio
D.
portfolio
Answers
Suggested answer: D

Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:

A.
quality audits
A.
quality audits
Answers
B.
process analysis
B.
process analysis
Answers
C.
statistical sampling
C.
statistical sampling
Answers
D.
benchmarking
D.
benchmarking
Answers
Suggested answer: A

Which Process Group's purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?

A.
Monitoring and Controlling
A.
Monitoring and Controlling
Answers
B.
Initiating
B.
Initiating
Answers
C.
Planning
C.
Planning
Answers
D.
Executing
D.
Executing
Answers
Suggested answer: A

The formal and informal interaction with others in an organization industry, or professional environment is known as:

A.
negotiation
A.
negotiation
Answers
B.
organizational theory
B.
organizational theory
Answers
C.
meeting
C.
meeting
Answers
D.
networking
D.
networking
Answers
Suggested answer: D

Which process is included in the Project Integration Management Knowledge Area?

A.
Manage Project Team
A.
Manage Project Team
Answers
B.
Collect Requirements
B.
Collect Requirements
Answers
C.
Sequence Activities
C.
Sequence Activities
Answers
D.
Direct and Manage Project Work
D.
Direct and Manage Project Work
Answers
Suggested answer: D

The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:

A.
Define Activities.
A.
Define Activities.
Answers
B.
Sequence Activities.
B.
Sequence Activities.
Answers
C.
Define Scope.
C.
Define Scope.
Answers
D.
Control Schedule.
D.
Control Schedule.
Answers
Suggested answer: A

Which document includes the project scope, major deliverables, assumptions, and constraints?

A.
Project charter
A.
Project charter
Answers
B.
Project scope statement
B.
Project scope statement
Answers
C.
Scope management plan
C.
Scope management plan
Answers
D.
Project document updates
D.
Project document updates
Answers
Suggested answer: B

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

A.
Bottom-up
A.
Bottom-up
Answers
B.
Parametric
B.
Parametric
Answers
C.
Analogous
C.
Analogous
Answers
D.
Three-point
D.
Three-point
Answers
Suggested answer: A

Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

A.
Cost management plan
A.
Cost management plan
Answers
B.
Quality management plan
B.
Quality management plan
Answers
C.
Communications management plan
C.
Communications management plan
Answers
D.
Risk management plan
D.
Risk management plan
Answers
Suggested answer: D

Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?

A.
Organizational process assets
A.
Organizational process assets
Answers
B.
A work breakdown structure
B.
A work breakdown structure
Answers
C.
The project management plan
C.
The project management plan
Answers
D.
Enterprise environmental factors
D.
Enterprise environmental factors
Answers
Suggested answer: A
Total 908 questions