The stakeholder register is an output of:

A.
Identify Stakeholders.
A.
Identify Stakeholders.
Answers
B.
Plan Stakeholder Management.
B.
Plan Stakeholder Management.
Answers
C.
Control Stakeholder Engagement.
C.
Control Stakeholder Engagement.
Answers
D.
Manage Stakeholder Engagement.
D.
Manage Stakeholder Engagement.
Answers
Suggested answer: A

An output of the Develop Project Team process is:

A.
change requests
A.
change requests
Answers
B.
team performance assessments
B.
team performance assessments
Answers
C.
project staff assignments
C.
project staff assignments
Answers
D.
project documents updates
D.
project documents updates
Answers
Suggested answer: B

Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?

A.
Portfolio
A.
Portfolio
Answers
B.
Project
B.
Project
Answers
C.
Program
C.
Program
Answers
D.
Operations
D.
Operations
Answers
Suggested answer: D

Which type of manager is assigned by the performing organization to lead the team that is responsible for achieving the project objectives?

A.
Program
A.
Program
Answers
B.
Functional
B.
Functional
Answers
C.
Project
C.
Project
Answers
D.
Portfolio
D.
Portfolio
Answers
Suggested answer: C

The approaches, tools, and data sources that will be used to perform risk management on a project are determined by the:

A.
Methodology
A.
Methodology
Answers
B.
Risk category
B.
Risk category
Answers
C.
Risk attitude
C.
Risk attitude
Answers
D.
Assumption analysis
D.
Assumption analysis
Answers
Suggested answer: A

An input of the Plan Procurement Management process is:

A.
Make-or-buy decisions.
A.
Make-or-buy decisions.
Answers
B.
Activity cost estimates.
B.
Activity cost estimates.
Answers
C.
Seller proposals.
C.
Seller proposals.
Answers
D.
Procurement documents.
D.
Procurement documents.
Answers
Suggested answer: B

Outputs of the Control Communications process include:

A.
expert judgment and change requests
A.
expert judgment and change requests
Answers
B.
work performance information and change requests
B.
work performance information and change requests
Answers
C.
project management plan updates and work performance information
C.
project management plan updates and work performance information
Answers
D.
issue logs and organizational process assets updates
D.
issue logs and organizational process assets updates
Answers
Suggested answer: B

Which organizational process assets update is performed during the Close Procurements process?

A.
Procurement audit
A.
Procurement audit
Answers
B.
Lessons learned
B.
Lessons learned
Answers
C.
Performance reporting
C.
Performance reporting
Answers
D.
Payment requests
D.
Payment requests
Answers
Suggested answer: B

The individual or group that provides resources and support for a project and is accountable for success is the:

A.
sponsor
A.
sponsor
Answers
B.
customer
B.
customer
Answers
C.
business partners
C.
business partners
Answers
D.
functional managers
D.
functional managers
Answers
Suggested answer: A

A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:

A.
budget at completion (BAC)
A.
budget at completion (BAC)
Answers
B.
earned value management (EVM)
B.
earned value management (EVM)
Answers
C.
to-complete performance index
C.
to-complete performance index
Answers
D.
cost performance index
D.
cost performance index
Answers
Suggested answer: C