The following is a network diagram for a project.

The total float for the project is how many days?

A.
3
A.
3
Answers
B.
5
B.
5
Answers
C.
7
C.
7
Answers
D.
9
D.
9
Answers
Suggested answer: A

Tools and techniques used in Direct and Manage Project Work include:

A.
Process analysis and expert judgment
A.
Process analysis and expert judgment
Answers
B.
Analytical techniques and a project management information system
B.
Analytical techniques and a project management information system
Answers
C.
Performance reviews and meetings
C.
Performance reviews and meetings
Answers
D.
Expert judgment and meetings
D.
Expert judgment and meetings
Answers
Suggested answer: D

Completion of the product scope is measured against the product:

A.
prototypes
A.
prototypes
Answers
B.
requirements
B.
requirements
Answers
C.
analyses
C.
analyses
Answers
D.
benchmarks
D.
benchmarks
Answers
Suggested answer: B

An issue log is an input to which Project Human Resource Management process?

A.
Manage Project Team
A.
Manage Project Team
Answers
B.
Acquire Project Team
B.
Acquire Project Team
Answers
C.
Plan Human Resource Management
C.
Plan Human Resource Management
Answers
D.
Develop Project Team
D.
Develop Project Team
Answers
Suggested answer: A

The component of the risk management plan that documents how risk activities will be recorded is called:

A.
tracking
A.
tracking
Answers
B.
scoping
B.
scoping
Answers
C.
timing
C.
timing
Answers
D.
defining
D.
defining
Answers
Suggested answer: A

Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?

A.
Information management systems
A.
Information management systems
Answers
B.
Work performance reports
B.
Work performance reports
Answers
C.
Stakeholder analysis
C.
Stakeholder analysis
Answers
D.
Data gathering and representation
D.
Data gathering and representation
Answers
Suggested answer: A

Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?

A.
Cause-and-effect diagram
A.
Cause-and-effect diagram
Answers
B.
Histogram
B.
Histogram
Answers
C.
Control chart
C.
Control chart
Answers
D.
Scatter diagram
D.
Scatter diagram
Answers
Suggested answer: D

High-level project risks are included in which document?

A.
Business case
A.
Business case
Answers
B.
Risk breakdown structure
B.
Risk breakdown structure
Answers
C.
Project charter
C.
Project charter
Answers
D.
Risk register
D.
Risk register
Answers
Suggested answer: C

The scope management plan and scope baseline are contained in:

A.
organizational process assets
A.
organizational process assets
Answers
B.
a requirements traceability matrix
B.
a requirements traceability matrix
Answers
C.
the project charter
C.
the project charter
Answers
D.
the project management plan
D.
the project management plan
Answers
Suggested answer: D

Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:

A.
portfolio
A.
portfolio
Answers
B.
program
B.
program
Answers
C.
selection
C.
selection
Answers
D.
sub portfolio
D.
sub portfolio
Answers
Suggested answer: B