ExamGecko
Home Home / PMI / CAPM

PMI CAPM Practice Test - Questions Answers, Page 28

Question list
Search
Search

Which quality tool incorporates the upper and lower specification limits allowed within an agreement?

A.
Control chart
A.
Control chart
Answers
B.
Flowchart
B.
Flowchart
Answers
C.
Checksheet
C.
Checksheet
Answers
D.
Pareto diagram
D.
Pareto diagram
Answers
Suggested answer: A

Analytical techniques are a tool and technique of which process in Project Procurement Management?

A.
Plan Procurement Management
A.
Plan Procurement Management
Answers
B.
Control Procurements
B.
Control Procurements
Answers
C.
Conduct Procurements
C.
Conduct Procurements
Answers
D.
Close Procurements
D.
Close Procurements
Answers
Suggested answer: C

The process of obtaining seller responses, selecting a seller, and awarding a contract is called:

A.
Close Procurements.
A.
Close Procurements.
Answers
B.
Control Procurements.
B.
Control Procurements.
Answers
C.
Plan Procurements.
C.
Plan Procurements.
Answers
D.
Conduct Procurements.
D.
Conduct Procurements.
Answers
Suggested answer: D

Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

A.
Business case
A.
Business case
Answers
B.
Work breakdown structure
B.
Work breakdown structure
Answers
C.
Requirements documentation
C.
Requirements documentation
Answers
D.
Risk register
D.
Risk register
Answers
Suggested answer: C

Which Process Group includes the Manage Stakeholder Engagement process?

A.
Executing
A.
Executing
Answers
B.
Planning
B.
Planning
Answers
C.
Monitoring and Controlling
C.
Monitoring and Controlling
Answers
D.
Initiating
D.
Initiating
Answers
Suggested answer: A

Funding limit reconciliation is a tool and technique of which Project Cost Management process?

A.
Estimate Costs
A.
Estimate Costs
Answers
B.
Control Costs
B.
Control Costs
Answers
C.
Plan Cost Management
C.
Plan Cost Management
Answers
D.
Determine Budget
D.
Determine Budget
Answers
Suggested answer: D

In complex projects/ initiating processes should be completed:

A.
Within a work package.
A.
Within a work package.
Answers
B.
In each phase of the project.
B.
In each phase of the project.
Answers
C.
To estimate schedule constraints.
C.
To estimate schedule constraints.
Answers
D.
To estimate resource allocations.
D.
To estimate resource allocations.
Answers
Suggested answer: B

A project manager requesting industry groups and consultants to recommend project intervention is relying on:

A.
Communication models.
A.
Communication models.
Answers
B.
Stakeholder participation.
B.
Stakeholder participation.
Answers
C.
Expert judgment
C.
Expert judgment
Answers
D.
Enterprise environmental factors.
D.
Enterprise environmental factors.
Answers
Suggested answer: C

The degree, amount, or volume of risk that an organization or individual will withstand is called risk:

A.
appetite
A.
appetite
Answers
B.
tolerance
B.
tolerance
Answers
C.
threshold
C.
threshold
Answers
D.
management
D.
management
Answers
Suggested answer: B

The following is a network diagram for a project.

What is the critical path for the project?

A.
A-B-D-G
A.
A-B-D-G
Answers
B.
A-B-E-G
B.
A-B-E-G
Answers
C.
A-C-F-G
C.
A-C-F-G
Answers
D.
A-C-E-G
D.
A-C-E-G
Answers
Suggested answer: C