ExamGecko
Home Home / PMI / CAPM

PMI CAPM Practice Test - Questions Answers, Page 26

Question list
Search
Search

Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

A.
Critical path method
A.
Critical path method
Answers
B.
Critical chain method
B.
Critical chain method
Answers
C.
Resource leveling
C.
Resource leveling
Answers
D.
Schedule network analysis
D.
Schedule network analysis
Answers
Suggested answer: B

The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:

A.
work package
A.
work package
Answers
B.
deliverable
B.
deliverable
Answers
C.
milestone
C.
milestone
Answers
D.
activity
D.
activity
Answers
Suggested answer: A

The scope management plan and scope baseline are contained in:

A.
organizational process assets
A.
organizational process assets
Answers
B.
a requirements traceability matrix
B.
a requirements traceability matrix
Answers
C.
the project charter
C.
the project charter
Answers
D.
the project management plan
D.
the project management plan
Answers
Suggested answer: D

Which Manage Communications tool or technique focuses on identifying and managing barriers?

A.
Communication methods
A.
Communication methods
Answers
B.
Information technology
B.
Information technology
Answers
C.
Communication models
C.
Communication models
Answers
D.
Information management systems
D.
Information management systems
Answers
Suggested answer: C

Which type of organizational structure is displayed in the diagram provided?

A.
Balanced matrix
A.
Balanced matrix
Answers
B.
Projectized
B.
Projectized
Answers
C.
Strong matrix
C.
Strong matrix
Answers
D.
Functional
D.
Functional
Answers
Suggested answer: B

Outputs of the Control Communications process include:

A.
expert judgment and change requests.
A.
expert judgment and change requests.
Answers
B.
work performance information and change requests.
B.
work performance information and change requests.
Answers
C.
organizational process asset updates and an issue log.
C.
organizational process asset updates and an issue log.
Answers
D.
project management plan updates and an issue log.
D.
project management plan updates and an issue log.
Answers
Suggested answer: B

In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?

A.
Technical approach
A.
Technical approach
Answers
B.
Technical capability
B.
Technical capability
Answers
C.
Business size and type
C.
Business size and type
Answers
D.
Production capacity and interest
D.
Production capacity and interest
Answers
Suggested answer: A

Stakeholder communication requirements should be included as a component of:

A.
enterprise environmental factors
A.
enterprise environmental factors
Answers
B.
organizational process assets
B.
organizational process assets
Answers
C.
the project management plan
C.
the project management plan
Answers
D.
the stakeholder register
D.
the stakeholder register
Answers
Suggested answer: C

Which element does a project charter contain?

A.
Management reserves
A.
Management reserves
Answers
B.
Work breakdown structure
B.
Work breakdown structure
Answers
C.
Stakeholder list
C.
Stakeholder list
Answers
D.
Stakeholder register
D.
Stakeholder register
Answers
Suggested answer: C

The following is a network diagram for a project.

What is the critical path for the project?

A.
A-B-C-F-G-I
A.
A-B-C-F-G-I
Answers
B.
A-B-C-F-H-I
B.
A-B-C-F-H-I
Answers
C.
A-D-E-F-G-I
C.
A-D-E-F-G-I
Answers
D.
A-D-E-F-H-I
D.
A-D-E-F-H-I
Answers
Suggested answer: A
Total 908 questions
Go to page: of 91