PMI CAPM Practice Test - Questions Answers, Page 24
List of questions
Question 231
Those who enter into a contractual agreement to provide services necessary for a project are:
Question 232
Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:
Question 233
Which items are an output of the Perform Integrated Change Control process?
Question 234
Which term describes an assessment of correctness?
Question 235
The cost baseline and project funding requirements are outputs of which process in Project Cost Management?
Question 236
The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:
Question 237
At the start of a typical project life cycle, costs are:
Question 238
Success is measured by benefits realization for a:
Question 239
Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?
Question 240
A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable.
This could have been avoided if the project team had implemented:
Question