The following chart contains information about the tasks in a project.

Based on the chart, what is the schedulevariance (SV) for Task 8?

A.
-2,000
A.
-2,000
Answers
B.
-1,000
B.
-1,000
Answers
C.
1,000
C.
1,000
Answers
D.
2,000
D.
2,000
Answers
Suggested answer: B

The following chart contains information about the tasks in a project.

Based on the chart, what is the cost variance (CV) for Task 6?

A.
-2,000
A.
-2,000
Answers
B.
0
B.
0
Answers
C.
1,000
C.
1,000
Answers
D.
2,000
D.
2,000
Answers
Suggested answer: D

The following chart contains information about the tasks in a project.

Based on the chart, what is the schedule performance index (5PI) for Task 4?

A.
0.83
A.
0.83
Answers
B.
0.9
B.
0.9
Answers
C.
1.11
C.
1.11
Answers
D.
1.33
D.
1.33
Answers
Suggested answer: C

One of the key benefits of the Plan Human Resource Management process is that it:

A.
outlines team selection guidelines and team member responsibilities.
A.
outlines team selection guidelines and team member responsibilities.
Answers
B.
establishes project roles and responsibilities.
B.
establishes project roles and responsibilities.
Answers
C.
improves teamwork, interpersonal skills, and competencies.
C.
improves teamwork, interpersonal skills, and competencies.
Answers
D.
provides an accurate appraisal of team member performance.
D.
provides an accurate appraisal of team member performance.
Answers
Suggested answer: B

Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?

A.
Decomposition
A.
Decomposition
Answers
B.
Inspection
B.
Inspection
Answers
C.
Project analysis
C.
Project analysis
Answers
D.
Document analysis
D.
Document analysis
Answers
Suggested answer: A

Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?

A.
Schedule network analysis
A.
Schedule network analysis
Answers
B.
Reserve analysis
B.
Reserve analysis
Answers
C.
Alternative analysis
C.
Alternative analysis
Answers
D.
Variance analysis
D.
Variance analysis
Answers
Suggested answer: D

A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?

A.
Work breakdown structure
A.
Work breakdown structure
Answers
B.
Requirements document
B.
Requirements document
Answers
C.
Project charter
C.
Project charter
Answers
D.
Project management plan
D.
Project management plan
Answers
Suggested answer: C

In the Define Activities process, the schedule management plan is used to:

A.
Capture the lessons learned from other projects for comparison.
A.
Capture the lessons learned from other projects for comparison.
Answers
B.
Contain the standard activity list.
B.
Contain the standard activity list.
Answers
C.
Document and support the project change requests.
C.
Document and support the project change requests.
Answers
D.
Prescribe the level of detail needed to manage the work.
D.
Prescribe the level of detail needed to manage the work.
Answers
Suggested answer: D

A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:

A.
risk management plan
A.
risk management plan
Answers
B.
human resource management plan
B.
human resource management plan
Answers
C.
scope management plan
C.
scope management plan
Answers
D.
procurement management plan
D.
procurement management plan
Answers
Suggested answer: D

A benefit of using virtual teams in the Acquire Project Team process is the reduction of the:

A.
cultural differences of team members
A.
cultural differences of team members
Answers
B.
possibility of communication misunderstandings
B.
possibility of communication misunderstandings
Answers
C.
costs associated with travel
C.
costs associated with travel
Answers
D.
costs associated with technology
D.
costs associated with technology
Answers
Suggested answer: C