PMI CAPM Practice Test - Questions Answers, Page 23

List of questions
Question 221

The following chart contains information about the tasks in a project.
Based on the chart, what is the schedulevariance (SV) for Task 8?
Question 222

The following chart contains information about the tasks in a project.
Based on the chart, what is the cost variance (CV) for Task 6?
Question 223

The following chart contains information about the tasks in a project.
Based on the chart, what is the schedule performance index (5PI) for Task 4?
Question 224

One of the key benefits of the Plan Human Resource Management process is that it:
Question 225

Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?
Question 226

Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?
Question 227

A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?
Question 228

In the Define Activities process, the schedule management plan is used to:
Question 229

A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:
Question 230

A benefit of using virtual teams in the Acquire Project Team process is the reduction of the:
Question