Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?

A.
Inspection
A.
Inspection
Answers
B.
Quality audits
B.
Quality audits
Answers
C.
Design of experiments
C.
Design of experiments
Answers
D.
Root cause analysis
D.
Root cause analysis
Answers
Suggested answer: D

A disadvantage associated with virtual teams is that they:

A.
Require communication technology that is not readily available.
A.
Require communication technology that is not readily available.
Answers
B.
Create difficulties when including people with disabilities.
B.
Create difficulties when including people with disabilities.
Answers
C.
Often cannot accommodate teams that work different hours or shifts.
C.
Often cannot accommodate teams that work different hours or shifts.
Answers
D.
Create the possibility for misunderstandings to arise.
D.
Create the possibility for misunderstandings to arise.
Answers
Suggested answer: D

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

A.
Performing
A.
Performing
Answers
B.
Storming
B.
Storming
Answers
C.
Norming
C.
Norming
Answers
D.
Forming
D.
Forming
Answers
Suggested answer: C

Which project risk listed in the table below is most likely to occur?

A.
1
A.
1
Answers
B.
2
B.
2
Answers
C.
3
C.
3
Answers
D.
4
D.
4
Answers
Suggested answer: B

Which is an enterprise environmental factor?

A.
Marketplace conditions
A.
Marketplace conditions
Answers
B.
Policies and procedures
B.
Policies and procedures
Answers
C.
Project files from previous projects
C.
Project files from previous projects
Answers
D.
Lessons learned from previous projects
D.
Lessons learned from previous projects
Answers
Suggested answer: A

Project Stakeholder Management focuses on:

A.
project staff assignments
A.
project staff assignments
Answers
B.
project tea m acquisition
B.
project tea m acquisition
Answers
C.
managing conflicting interests
C.
managing conflicting interests
Answers
D.
communication methods
D.
communication methods
Answers
Suggested answer: C

A risk that arises as a direct result of implementing a risk response is called a:

A.
contingent risk
A.
contingent risk
Answers
B.
residual risk
B.
residual risk
Answers
C.
potential risk
C.
potential risk
Answers
D.
secondary risk
D.
secondary risk
Answers
Suggested answer: D

The purpose of developing a project scope management plan is to:

A.
Manage the timely completion of the project.
A.
Manage the timely completion of the project.
Answers
B.
Ensure that the project includes all of the work required.
B.
Ensure that the project includes all of the work required.
Answers
C.
Make sure the project will satisfy the needs for which it was begun.
C.
Make sure the project will satisfy the needs for which it was begun.
Answers
D.
Reduce the risk of negative events in the project.
D.
Reduce the risk of negative events in the project.
Answers
Suggested answer: B

A tool and technique used in the Develop Project Charter process is:

A.
change control tools
A.
change control tools
Answers
B.
expert judgment
B.
expert judgment
Answers
C.
meetings
C.
meetings
Answers
D.
analytical techniques
D.
analytical techniques
Answers
Suggested answer: B

The following chart contains information about the tasks in a project.

Based on the chart, what is the cost performance index (CPI) for Task 2?

A.
0.8
A.
0.8
Answers
B.
1
B.
1
Answers
C.
1.25
C.
1.25
Answers
D.
1.8
D.
1.8
Answers
Suggested answer: C