PMI CAPM Practice Test - Questions Answers, Page 20

List of questions
Question 191

Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?
Question 192

Which stakeholder approves a project's result?
Question 193

Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?
Question 194

Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:
Question 195

Perform Integrated Change Control is the process of:
Question 196

When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:
Question 197

Which action is included in the Control Costs process?
Question 198

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?
Question 199

A complete set of concepts, terms, and activities that make up an area of specialization is known as:
Question 200

The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:
Question