Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

A.
100
A.
100
Answers
B.
120
B.
120
Answers
C.
1,000
C.
1,000
Answers
D.
1,200
D.
1,200
Answers
Suggested answer: A

Which stakeholder approves a project's result?

A.
Customer
A.
Customer
Answers
B.
Sponsor
B.
Sponsor
Answers
C.
Seller
C.
Seller
Answers
D.
Functional manager
D.
Functional manager
Answers
Suggested answer: A

Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?

A.
Collect Requirements
A.
Collect Requirements
Answers
B.
Plan Scope Management
B.
Plan Scope Management
Answers
C.
Define Scope
C.
Define Scope
Answers
D.
Define Activities
D.
Define Activities
Answers
Suggested answer: A

Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:

A.
Available organizational assets
A.
Available organizational assets
Answers
B.
Project staff assignments
B.
Project staff assignments
Answers
C.
Interpersonal skills
C.
Interpersonal skills
Answers
D.
Enterprise environmental factors
D.
Enterprise environmental factors
Answers
Suggested answer: A

Perform Integrated Change Control is the process of:

A.
Reviewing, approving, and managing all change requests
A.
Reviewing, approving, and managing all change requests
Answers
B.
Facilitating change management, manuals, or automation tools
B.
Facilitating change management, manuals, or automation tools
Answers
C.
Comparing actual results with planned results in order to expand or change a project
C.
Comparing actual results with planned results in order to expand or change a project
Answers
D.
Documenting changes according to the change control system by the change control board
D.
Documenting changes according to the change control system by the change control board
Answers
Suggested answer: A

When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:

A.
lead
A.
lead
Answers
B.
lag
B.
lag
Answers
C.
mandatory dependency
C.
mandatory dependency
Answers
D.
internal dependency
D.
internal dependency
Answers
Suggested answer: A

Which action is included in the Control Costs process?

A.
Identify how the project costs will be planned, structured, and controlled
A.
Identify how the project costs will be planned, structured, and controlled
Answers
B.
Determine policies, objectives, and responsibilities to satisfy stakeholder needs
B.
Determine policies, objectives, and responsibilities to satisfy stakeholder needs
Answers
C.
Develop an approximation of the monetary resources needed to complete project activities
C.
Develop an approximation of the monetary resources needed to complete project activities
Answers
D.
Monitor cost performance to isolate and understand variances from the approved cost baseline
D.
Monitor cost performance to isolate and understand variances from the approved cost baseline
Answers
Suggested answer: D

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

A.
0.03
A.
0.03
Answers
B.
0.06
B.
0.06
Answers
C.
0.10
C.
0.10
Answers
D.
0.50
D.
0.50
Answers
Suggested answer: B

A complete set of concepts, terms, and activities that make up an area of specialization is known as:

A.
a Knowledge Area
A.
a Knowledge Area
Answers
B.
a Process Group
B.
a Process Group
Answers
C.
program management
C.
program management
Answers
D.
portfolio management
D.
portfolio management
Answers
Suggested answer: A

The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:

A.
exploit
A.
exploit
Answers
B.
avoid
B.
avoid
Answers
C.
mitigate
C.
mitigate
Answers
D.
share
D.
share
Answers
Suggested answer: C
Total 908 questions