ExamGecko
Home Home / PMI / CAPM

PMI CAPM Practice Test - Questions Answers, Page 19

Question list
Search
Search

The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

A.
recognition and rewards
A.
recognition and rewards
Answers
B.
compliance
B.
compliance
Answers
C.
staff acquisition
C.
staff acquisition
Answers
D.
training needs
D.
training needs
Answers
Suggested answer: D

Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

A.
Continuous
A.
Continuous
Answers
B.
Discrete
B.
Discrete
Answers
C.
Regulated
C.
Regulated
Answers
D.
Arbitrary
D.
Arbitrary
Answers
Suggested answer: A

A graphic display of project team members and their reporting relationships is known as a:

A.
Resource calendar.
A.
Resource calendar.
Answers
B.
Project organization chart.
B.
Project organization chart.
Answers
C.
Resource breakdown structure (RBS).
C.
Resource breakdown structure (RBS).
Answers
D.
Responsibility assignment matrix (RAM).
D.
Responsibility assignment matrix (RAM).
Answers
Suggested answer: B

Which item is a cost of conformance?

A.
Training
A.
Training
Answers
B.
Liabilities
B.
Liabilities
Answers
C.
Lost business
C.
Lost business
Answers
D.
Scrap
D.
Scrap
Answers
Suggested answer: A

Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?

A.
Collaboration
A.
Collaboration
Answers
B.
Negotiation
B.
Negotiation
Answers
C.
Decision making
C.
Decision making
Answers
D.
Influencing
D.
Influencing
Answers
Suggested answer: D

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

A.
Estimate Costs
A.
Estimate Costs
Answers
B.
Control Costs
B.
Control Costs
Answers
C.
Plan Cost Management
C.
Plan Cost Management
Answers
D.
Determine Budget
D.
Determine Budget
Answers
Suggested answer: D

In project management, a temporary project can be:

A.
Completed without planning
A.
Completed without planning
Answers
B.
A routine business process
B.
A routine business process
Answers
C.
Long in duration
C.
Long in duration
Answers
D.
Ongoing to produce goods
D.
Ongoing to produce goods
Answers
Suggested answer: C

Which document in the project management plan can be updated in the Plan Procurement Management process?

A.
Budget estimates
A.
Budget estimates
Answers
B.
Risk matrix
B.
Risk matrix
Answers
C.
Requirements documentation
C.
Requirements documentation
Answers
D.
Procurement documents
D.
Procurement documents
Answers
Suggested answer: C

Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?

A.
Uniform
A.
Uniform
Answers
B.
Continuous
B.
Continuous
Answers
C.
Discrete
C.
Discrete
Answers
D.
Linear
D.
Linear
Answers
Suggested answer: C

Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

A.
Update
A.
Update
Answers
B.
Preventive action
B.
Preventive action
Answers
C.
Defect repair
C.
Defect repair
Answers
D.
Corrective action
D.
Corrective action
Answers
Suggested answer: D
Total 908 questions
Go to page: of 91