Which tools or techniques are used during the Close Project or Phase process?

A.
Reserve analysis and expert judgment
A.
Reserve analysis and expert judgment
Answers
B.
Facilitation techniques and meetings
B.
Facilitation techniques and meetings
Answers
C.
Expert judgment and analytical techniques
C.
Expert judgment and analytical techniques
Answers
D.
Performance reviews and meetings
D.
Performance reviews and meetings
Answers
Suggested answer: C

When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:

A.
improvement
A.
improvement
Answers
B.
program
B.
program
Answers
C.
result
C.
result
Answers
D.
portfolio
D.
portfolio
Answers
Suggested answer: A

The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

A.
management
A.
management
Answers
B.
response
B.
response
Answers
C.
tolerance
C.
tolerance
Answers
D.
appetite
D.
appetite
Answers
Suggested answer: D

The zero duration of milestones in project planning occurs because milestones:

A.
Are unpredictable and challenge the Plan Schedule Management process.
A.
Are unpredictable and challenge the Plan Schedule Management process.
Answers
B.
Occur at random times in the project plans.
B.
Occur at random times in the project plans.
Answers
C.
Represent a moment in time such as a significant project point or event.
C.
Represent a moment in time such as a significant project point or event.
Answers
D.
Represent both significant and insignificant points in the project and are difficult to anticipate.
D.
Represent both significant and insignificant points in the project and are difficult to anticipate.
Answers
Suggested answer: C

Which type of graphic is displayed below?

A.
Work breakdown structure
A.
Work breakdown structure
Answers
B.
Context diagram
B.
Context diagram
Answers
C.
Control chart
C.
Control chart
Answers
D.
Pareto diagram
D.
Pareto diagram
Answers
Suggested answer: A

An example of a group decision-making technique is:

A.
nominal group technique
A.
nominal group technique
Answers
B.
majority
B.
majority
Answers
C.
affinity diagram
C.
affinity diagram
Answers
D.
multi-criteria decision analysis
D.
multi-criteria decision analysis
Answers
Suggested answer: B

Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

A.
Procurement documents
A.
Procurement documents
Answers
B.
Inspection and audits
B.
Inspection and audits
Answers
C.
Estimate budget
C.
Estimate budget
Answers
D.
Risk register
D.
Risk register
Answers
Suggested answer: B

Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

A.
Influencing
A.
Influencing
Answers
B.
Motivation
B.
Motivation
Answers
C.
Negotiation
C.
Negotiation
Answers
D.
Trust building
D.
Trust building
Answers
Suggested answer: B

The following is a network diagram for a project.

The shortest non-critical path for the project is how many days in duration?

A.
10
A.
10
Answers
B.
12
B.
12
Answers
C.
14
C.
14
Answers
D.
16
D.
16
Answers
Suggested answer: A

The following is a network diagram for a project.

The critical path for the project is how many days in duration?

A.
10
A.
10
Answers
B.
12
B.
12
Answers
C.
14
C.
14
Answers
D.
17
D.
17
Answers
Suggested answer: D
Total 908 questions