Which tools or techniques are used during the Close Project or Phase process?

Reserve analysis and expert judgment
Reserve analysis and expert judgment
Facilitation techniques and meetings
Facilitation techniques and meetings
Expert judgment and analytical techniques
Expert judgment and analytical techniques
Performance reviews and meetings
Performance reviews and meetings
Suggested answer: C
asked 23/09/2024
mohamed mamdouh
46 questions

Question 172

Report Export Collapse

When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:

improvement
improvement
program
program
result
result
portfolio
portfolio
Suggested answer: A
asked 23/09/2024
Shan Panikker
34 questions

Question 173

Report Export Collapse

The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

management
management
response
response
tolerance
tolerance
appetite
appetite
Suggested answer: D
asked 23/09/2024
Azfar khan
46 questions

Question 174

Report Export Collapse

The zero duration of milestones in project planning occurs because milestones:

Are unpredictable and challenge the Plan Schedule Management process.
Are unpredictable and challenge the Plan Schedule Management process.
Occur at random times in the project plans.
Occur at random times in the project plans.
Represent a moment in time such as a significant project point or event.
Represent a moment in time such as a significant project point or event.
Represent both significant and insignificant points in the project and are difficult to anticipate.
Represent both significant and insignificant points in the project and are difficult to anticipate.
Suggested answer: C
asked 23/09/2024
Muath Ahmed Saleh AlShuwaer
44 questions

Question 175

Report Export Collapse

Which type of graphic is displayed below?

PMI CAPM image Question 175 55199 09232024001321000000

Work breakdown structure
Work breakdown structure
Context diagram
Context diagram
Control chart
Control chart
Pareto diagram
Pareto diagram
Suggested answer: A
asked 23/09/2024
Sumit Sengupta
47 questions

Question 176

Report Export Collapse

An example of a group decision-making technique is:

nominal group technique
nominal group technique
majority
majority
affinity diagram
affinity diagram
multi-criteria decision analysis
multi-criteria decision analysis
Suggested answer: B
asked 23/09/2024
Echo Wind
31 questions

Question 177

Report Export Collapse

Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

Procurement documents
Procurement documents
Inspection and audits
Inspection and audits
Estimate budget
Estimate budget
Risk register
Risk register
Suggested answer: B
asked 23/09/2024
Liusel Herrera Garcia
50 questions

Question 178

Report Export Collapse

Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

Influencing
Influencing
Motivation
Motivation
Negotiation
Negotiation
Trust building
Trust building
Suggested answer: B
asked 23/09/2024
Donnie Roach
32 questions

Question 179

Report Export Collapse

The following is a network diagram for a project.

PMI CAPM image Question 179 55203 09232024001321000000

The shortest non-critical path for the project is how many days in duration?

10
10
12
12
14
14
16
16
Suggested answer: A
asked 23/09/2024
Tanpisit Songvechkasam
37 questions

Question 180

Report Export Collapse

The following is a network diagram for a project.

PMI CAPM image Question 180 55204 09232024001321000000

The critical path for the project is how many days in duration?

10
10
12
12
14
14
17
17
Suggested answer: D