PMI CAPM Practice Test - Questions Answers, Page 27
List of questions
Question 261
The following is a network diagram for a project.
How many possible paths are identified for this project?
Question 262
The following is a network diagram for a project.
The free float for Activity H is how many days?
Question 263
Every project creates a unique product, service, or result that may be:
Question 264
Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:
Question 265
The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:
Question 266
Whose approval may be required for change requests after change control board (CCB) approval?
Question 267
The primary benefit of the Plan Schedule Management process is that it:
Question 268
Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?
Question 269
Variance and trend analysis is a tool and technique used in which process?
Question 270
An intentional activity to modify a nonconforming product or product component is called:
Question