Question 291

Report
Export
Collapse

A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller's performance. The most appropriate agreement with the supplier is:

Cost Plus Incentive Fee (CPIF).
Cost Plus Incentive Fee (CPIF).
Fixed Price Incentive Fee (FPIF).
Fixed Price Incentive Fee (FPIF).
Cost Plus Award Fee (CPAF).
Cost Plus Award Fee (CPAF).
Fixed Price with Economic Price Adjustment (FP-EPA).
Fixed Price with Economic Price Adjustment (FP-EPA).
Suggested answer: B
asked 23/09/2024
Ruud God
36 questions

Question 292

Report
Export
Collapse

Which enterprise environmental factors may influence Plan Schedule Management?

Cultural views regarding time schedules and professional and ethical behaviors
Cultural views regarding time schedules and professional and ethical behaviors
Historical information and change control procedures
Historical information and change control procedures
Risk control procedures and the probability and impact matrix
Risk control procedures and the probability and impact matrix
Resource availability and organizational culture and structure
Resource availability and organizational culture and structure
Suggested answer: D
asked 23/09/2024
Kelvin Galabuzi
37 questions

Question 293

Report
Export
Collapse

Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?

Internal
Internal
External
External
Discretionary
Discretionary
Mandatory
Mandatory
Suggested answer: C
asked 23/09/2024
louishn vn
33 questions

Question 294

Report
Export
Collapse

When the business objectives of an organization change, project goals need to be:

realigned.
realigned.
performed.
performed.
improved.
improved.
controlled.
controlled.
Suggested answer: A
asked 23/09/2024
Mathijs Sijm
25 questions

Question 295

Report
Export
Collapse

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?

Activity network diagrams
Activity network diagrams
Affinity diagrams
Affinity diagrams
Matrix diagrams
Matrix diagrams
Interrelationship digraphs
Interrelationship digraphs
Suggested answer: B
asked 23/09/2024
Salvatore Andrisani
40 questions

Question 296

Report
Export
Collapse

A project manager who communicates to the project team though email is using which type of communication?

Formal
Formal
Informal r
Informal r
Horizontal
Horizontal
Unofficial
Unofficial
Suggested answer: B
asked 23/09/2024
Muhammad Waheed
41 questions

Question 297

Report
Export
Collapse

An input to the Perform Integrated Change Control process is:

expert judgment
expert judgment
seller proposals
seller proposals
the project charter
the project charter
the project management plan
the project management plan
Suggested answer: D
asked 23/09/2024
Krishan Randitha
42 questions

Question 298

Report
Export
Collapse

Which tool or technique is required in order to determine the project budget?

Cost of quality
Cost of quality
Historical relationships
Historical relationships
Project management software
Project management software
Forecasting
Forecasting
Suggested answer: B
asked 23/09/2024
Ravindra MG
27 questions

Question 299

Report
Export
Collapse

Requirements documentation will typically contain at least:

Stakeholder requirements, staffing requirements, and transition requirements.
Stakeholder requirements, staffing requirements, and transition requirements.
Business requirements, the stakeholder register, and functional requirements.
Business requirements, the stakeholder register, and functional requirements.
Stakeholder impact, budget requirements, and communications requirements.
Stakeholder impact, budget requirements, and communications requirements.
Business objectives, stakeholder impact, and functional requirements.
Business objectives, stakeholder impact, and functional requirements.
Suggested answer: D
asked 23/09/2024
Fabio Morais Melo
37 questions

Question 300

Report
Export
Collapse

Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?

Define Activities
Define Activities
Direct and Manage Project Work
Direct and Manage Project Work
Develop Project Management Plan
Develop Project Management Plan
Develop Project Charter
Develop Project Charter
Suggested answer: D

Explanation:

Topic 3, Volume C

asked 23/09/2024
Michael Bays
33 questions