ExamGecko
Home / PMI / CAPM / List of questions
Ask Question

PMI CAPM Practice Test - Questions Answers, Page 30

Add to Whishlist

List of questions

Question 291

Report Export Collapse

A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller's performance. The most appropriate agreement with the supplier is:

Become a Premium Member for full access
  Unlock Premium Member

Question 292

Report Export Collapse

Which enterprise environmental factors may influence Plan Schedule Management?

Become a Premium Member for full access
  Unlock Premium Member

Question 293

Report Export Collapse

Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?

Become a Premium Member for full access
  Unlock Premium Member

Question 294

Report Export Collapse

When the business objectives of an organization change, project goals need to be:

Become a Premium Member for full access
  Unlock Premium Member

Question 295

Report Export Collapse

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?

Become a Premium Member for full access
  Unlock Premium Member

Question 296

Report Export Collapse

A project manager who communicates to the project team though email is using which type of communication?

Become a Premium Member for full access
  Unlock Premium Member

Question 297

Report Export Collapse

An input to the Perform Integrated Change Control process is:

Become a Premium Member for full access
  Unlock Premium Member

Question 298

Report Export Collapse

Which tool or technique is required in order to determine the project budget?

Become a Premium Member for full access
  Unlock Premium Member

Question 299

Report Export Collapse

Requirements documentation will typically contain at least:

Become a Premium Member for full access
  Unlock Premium Member

Question 300

Report Export Collapse

Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?

Become a Premium Member for full access
  Unlock Premium Member
Total 908 questions
Go to page: of 91