What is the number of stakeholders, if the project has 28 potential communication channels?

A.
7
A.
7
Answers
B.
8
B.
8
Answers
C.
14
C.
14
Answers
D.
16
D.
16
Answers
Suggested answer: B

Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?

A.
Mitigate
A.
Mitigate
Answers
B.
Transfer
B.
Transfer
Answers
C.
Share
C.
Share
Answers
D.
Avoid
D.
Avoid
Answers
Suggested answer: C

Which activity is an input to the Conduct Procurements process?

A.
Organizational process assets
A.
Organizational process assets
Answers
B.
Resource availability
B.
Resource availability
Answers
C.
Perform Integrated Change Control
C.
Perform Integrated Change Control
Answers
D.
Team performance assessment
D.
Team performance assessment
Answers
Suggested answer: A

Which of the following investigates the likelihood that each specific risk will occur?

A.
Risk register
A.
Risk register
Answers
B.
Risk audits
B.
Risk audits
Answers
C.
Risk urgency assessment
C.
Risk urgency assessment
Answers
D.
Risk probability and impact assessment
D.
Risk probability and impact assessment
Answers
Suggested answer: D

What is a hierarchically organized depiction of the identified project risks arranged by risk category?

A.
Risk register
A.
Risk register
Answers
B.
Risk breakdown structure (RBS)
B.
Risk breakdown structure (RBS)
Answers
C.
Risk management plan
C.
Risk management plan
Answers
D.
Risk category
D.
Risk category
Answers
Suggested answer: B

Which tool or technique of Plan Quality involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?

A.
Histogram
A.
Histogram
Answers
B.
Quality audits
B.
Quality audits
Answers
C.
Benchmarking
C.
Benchmarking
Answers
D.
Performance measurement analysis
D.
Performance measurement analysis
Answers
Suggested answer: C

Taking out insurance in relation to risk management is called what?

A.
Transference
A.
Transference
Answers
B.
Avoidance
B.
Avoidance
Answers
C.
Exploring
C.
Exploring
Answers
D.
Mitigation
D.
Mitigation
Answers
Suggested answer: A

During which process group is the quality policy determined?

A.
Initiating
A.
Initiating
Answers
B.
Executing
B.
Executing
Answers
C.
Planning
C.
Planning
Answers
D.
Controlling
D.
Controlling
Answers
Suggested answer: C

Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?

A.
Analogous
A.
Analogous
Answers
B.
Parametric
B.
Parametric
Answers
C.
Bottom-up
C.
Bottom-up
Answers
D.
Top-down
D.
Top-down
Answers
Suggested answer: A

What is the difference between the critical path and the critical chain?

A.
Scope changes
A.
Scope changes
Answers
B.
Resource limitations
B.
Resource limitations
Answers
C.
Risk analysis
C.
Risk analysis
Answers
D.
Quality audits
D.
Quality audits
Answers
Suggested answer: B