Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?

A.
Organizational standard processes
A.
Organizational standard processes
Answers
B.
Marketplace conditions
B.
Marketplace conditions
Answers
C.
Historical information
C.
Historical information
Answers
D.
Templates
D.
Templates
Answers
Suggested answer: B

The Define Scope process is in which of the following Process Groups?

A.
Initiating
A.
Initiating
Answers
B.
Planning
B.
Planning
Answers
C.
Monitoring and Controlling
C.
Monitoring and Controlling
Answers
D.
Executing
D.
Executing
Answers
Suggested answer: B

Organizations perceive risks as:

A.
events that will inevitably impact project and organizational objectives.
A.
events that will inevitably impact project and organizational objectives.
Answers
B.
the effect of uncertainty on their project and organizational objectives.
B.
the effect of uncertainty on their project and organizational objectives.
Answers
C.
events which could have a negative impact on project and organizational objectives.
C.
events which could have a negative impact on project and organizational objectives.
Answers
D.
the negative impact of undesired events on their project and organizational objectives.
D.
the negative impact of undesired events on their project and organizational objectives.
Answers
Suggested answer: B

In an organization with a projectized organizational structure, who controls the project budget?

A.
Functional manager
A.
Functional manager
Answers
B.
Project manager
B.
Project manager
Answers
C.
Program manager
C.
Program manager
Answers
D.
Project management office
D.
Project management office
Answers
Suggested answer: B

Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?

A.
The customer and functional managers
A.
The customer and functional managers
Answers
B.
The risk owners and stakeholders
B.
The risk owners and stakeholders
Answers
C.
The sponsors and stakeholders
C.
The sponsors and stakeholders
Answers
D.
The project management team
D.
The project management team
Answers
Suggested answer: D

Which enterprise environmental factors are considered during Estimate Costs?

A.
Market conditions and published commercial information
A.
Market conditions and published commercial information
Answers
B.
Company structure and market conditions
B.
Company structure and market conditions
Answers
C.
Commercial information and company structure
C.
Commercial information and company structure
Answers
D.
Existing human resources and market conditions
D.
Existing human resources and market conditions
Answers
Suggested answer: A

Who selects the appropriate processes for a project?

A.
Project stakeholders
A.
Project stakeholders
Answers
B.
Project sponsor and project stakeholder
B.
Project sponsor and project stakeholder
Answers
C.
Project manager and project team
C.
Project manager and project team
Answers
D.
Project manager and project sponsor
D.
Project manager and project sponsor
Answers
Suggested answer: C

The scope management plan is a subsidiary of which project document?

A.
Schedule management plan
A.
Schedule management plan
Answers
B.
Project management plan
B.
Project management plan
Answers
C.
Quality management plan
C.
Quality management plan
Answers
D.
Resource management plan
D.
Resource management plan
Answers
Suggested answer: B

Which is an example of Administer Procurements?

A.
Negotiating the contract
A.
Negotiating the contract
Answers
B.
Authorizing contractor work
B.
Authorizing contractor work
Answers
C.
Developing the statement of work
C.
Developing the statement of work
Answers
D.
Establishing evaluation criteria
D.
Establishing evaluation criteria
Answers
Suggested answer: B

An input to the Create WBS process is a:

A.
project charter.
A.
project charter.
Answers
B.
stakeholder register.
B.
stakeholder register.
Answers
C.
project scope statement.
C.
project scope statement.
Answers
D.
requirements traceability matrix.
D.
requirements traceability matrix.
Answers
Suggested answer: C