Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:

A.
updates.
A.
updates.
Answers
B.
defect repairs.
B.
defect repairs.
Answers
C.
preventive actions.
C.
preventive actions.
Answers
D.
corrective actions.
D.
corrective actions.
Answers
Suggested answer: A

Which provides the basic framework for managing a project?

A.
Project life cycle
A.
Project life cycle
Answers
B.
Work breakdown structure (WBS)
B.
Work breakdown structure (WBS)
Answers
C.
Enterprise environmental factors
C.
Enterprise environmental factors
Answers
D.
Project initiation
D.
Project initiation
Answers
Suggested answer: A

A tool and technique used during the Perform Qualitative Risk Analysis process is:

A.
risk data quality assessment.
A.
risk data quality assessment.
Answers
B.
variance and trend analysis.
B.
variance and trend analysis.
Answers
C.
data gathering and representation techniques.
C.
data gathering and representation techniques.
Answers
D.
risk audits.
D.
risk audits.
Answers
Suggested answer: A

In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:

A.
enterprise environmental factors.
A.
enterprise environmental factors.
Answers
B.
organizational process assets.
B.
organizational process assets.
Answers
C.
project management plan,
C.
project management plan,
Answers
D.
project funding requirements.
D.
project funding requirements.
Answers
Suggested answer: A

The milestone list is an input to which process from the Planning Process Group?

A.
Define Activities
A.
Define Activities
Answers
B.
Estimate Activity Durations
B.
Estimate Activity Durations
Answers
C.
Estimate Activity Resources
C.
Estimate Activity Resources
Answers
D.
Sequence Activities
D.
Sequence Activities
Answers
Suggested answer: D

Quality metrics are an output of which process?

A.
Plan Quality
A.
Plan Quality
Answers
B.
Perform Quality Control
B.
Perform Quality Control
Answers
C.
Perform Quality Assurance
C.
Perform Quality Assurance
Answers
D.
Perform Qualitative Risk Analysis
D.
Perform Qualitative Risk Analysis
Answers
Suggested answer: A

The purpose of inspection in Perform Quality Control is to keep errors:

A.
in line with a measured degree of conformity.
A.
in line with a measured degree of conformity.
Answers
B.
out of the hands of the customer.
B.
out of the hands of the customer.
Answers
C.
in a specified range of acceptable results.
C.
in a specified range of acceptable results.
Answers
D.
out of the process.
D.
out of the process.
Answers
Suggested answer: B

An input to the Perform Quantitative Risk Analysis process is the:

A.
quality management plan.
A.
quality management plan.
Answers
B.
project management plan.
B.
project management plan.
Answers
C.
communications management plan.
C.
communications management plan.
Answers
D.
schedule management plan.
D.
schedule management plan.
Answers
Suggested answer: D

When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:

A.
divided among each of the phases or subprojects.
A.
divided among each of the phases or subprojects.
Answers
B.
repeated for each of the phases or subprojects.
B.
repeated for each of the phases or subprojects.
Answers
C.
linked to specific phases or subprojects.
C.
linked to specific phases or subprojects.
Answers
D.
integrated for specific phases or subprojects.
D.
integrated for specific phases or subprojects.
Answers
Suggested answer: B

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

A.
US$S000
A.
US$S000
Answers
B.
US$9500
B.
US$9500
Answers
C.
US$10,000
C.
US$10,000
Answers
D.
US$12,500
D.
US$12,500
Answers
Suggested answer: D