PMI CAPM Practice Test - Questions Answers, Page 52
List of questions
Question 511
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?
Question 512
Which of the following strategic considerations often results in project authorization?
Question 513
In which Process Group are lessons learned documented?
Question 514
Tools and techniques used for Plan Communications include the communication:
Question 515
In Project Cost Management, which input is exclusive to the Determine Budget process?
Question 516
Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?
Question 517
A tool or technique in Perform Quality Control that a project manager would use is:
Question 518
The precedence diagramming method (PDM) is also known as:
Question 519
Change request status updates are an output of which process?
Question 520
As the project progresses, which of the following is routinely collected from the project activities?
Question