Question 511

Report
Export
Collapse

Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?

Product scope description
Product scope description
Procurement statement of work
Procurement statement of work
Project schedule
Project schedule
Work breakdown structure (WBS)
Work breakdown structure (WBS)
Suggested answer: B
asked 23/09/2024
Mina Shaker
45 questions

Question 512

Report
Export
Collapse

Which of the following strategic considerations often results in project authorization?

Customer requests and/or issue resolution
Customer requests and/or issue resolution
Stakeholder expectations and/or strategic opportunity (business need)
Stakeholder expectations and/or strategic opportunity (business need)
Technological advancement and/or senior executive request
Technological advancement and/or senior executive request
Market demand and/or legal requirements
Market demand and/or legal requirements
Suggested answer: D
asked 23/09/2024
Delano van Kleinwee
40 questions

Question 513

Report
Export
Collapse

In which Process Group are lessons learned documented?

Planning
Planning
Closing
Closing
Executing
Executing
Initiating
Initiating
Suggested answer: B
asked 23/09/2024
Bruno Soriano
34 questions

Question 514

Report
Export
Collapse

Tools and techniques used for Plan Communications include the communication:

requirements analysis, communication technology, communication models, and communication methods.
requirements analysis, communication technology, communication models, and communication methods.
methods, stakeholder register, communication technology, and communication models.
methods, stakeholder register, communication technology, and communication models.
requirements, communication technology, communication requirements analysis, and communication methods.
requirements, communication technology, communication requirements analysis, and communication methods.
management plan, communication technology, communication models, and communication requirements analysis.
management plan, communication technology, communication models, and communication requirements analysis.
Suggested answer: A
asked 23/09/2024
Ahmed Alghadeer
31 questions

Question 515

Report
Export
Collapse

In Project Cost Management, which input is exclusive to the Determine Budget process?

Scope baseline
Scope baseline
Organizational process assets
Organizational process assets
Project schedule
Project schedule
Resource calendars
Resource calendars
Suggested answer: D
asked 23/09/2024
Talal Elemam
51 questions

Question 516

Report
Export
Collapse

Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?

Compromising
Compromising
Collaborating
Collaborating
Smoothing
Smoothing
Problem Solving
Problem Solving
Suggested answer: C
asked 23/09/2024
Alex Rector
30 questions

Question 517

Report
Export
Collapse

A tool or technique in Perform Quality Control that a project manager would use is:

quality audits.
quality audits.
process analysis.
process analysis.
benchmarking.
benchmarking.
inspection.
inspection.
Suggested answer: D
asked 23/09/2024
James Scott
42 questions

Question 518

Report
Export
Collapse

The precedence diagramming method (PDM) is also known as:

Arrow Diagram.
Arrow Diagram.
Critical Path Methodology (CPM).
Critical Path Methodology (CPM).
Activity-On-Node (AON).
Activity-On-Node (AON).
schedule network diagram.
schedule network diagram.
Suggested answer: C
asked 23/09/2024
Sharon Sandhu
43 questions

Question 519

Report
Export
Collapse

Change request status updates are an output of which process?

Perform Integrated Change Control
Perform Integrated Change Control
Direct and Manage Project Execution
Direct and Manage Project Execution
Close Project or Phase
Close Project or Phase
Monitor and Control Project Work
Monitor and Control Project Work
Suggested answer: A
asked 23/09/2024
Marcos Antonio Dantas
42 questions

Question 520

Report
Export
Collapse

As the project progresses, which of the following is routinely collected from the project activities?

Communication management activities
Communication management activities
Change requests
Change requests
Configuration verification and audit
Configuration verification and audit
Work performance information
Work performance information
Suggested answer: D
asked 23/09/2024
Andrew Vogel
40 questions
Total 908 questions