PMI CAPM Practice Test - Questions Answers, Page 52
List of questions
Question 511
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?
Question 512
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Which of the following strategic considerations often results in project authorization?
Question 513
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
In which Process Group are lessons learned documented?
Question 514
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Tools and techniques used for Plan Communications include the communication:
Question 515
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
In Project Cost Management, which input is exclusive to the Determine Budget process?
Question 516
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?
Question 517
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A tool or technique in Perform Quality Control that a project manager would use is:
Question 518
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
The precedence diagramming method (PDM) is also known as:
Question 519
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Change request status updates are an output of which process?
Question 520
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
As the project progresses, which of the following is routinely collected from the project activities?
Question