ExamGecko
Home Home / PMI / CAPM

PMI CAPM Practice Test - Questions Answers, Page 60

Question list
Search
Search

Which of the following is an input to the Perform Qualitative Risk Analysis process?

A.
Risk register
A.
Risk register
Answers
B.
Risk data quality assessment
B.
Risk data quality assessment
Answers
C.
Risk categorization
C.
Risk categorization
Answers
D.
Risk urgency
D.
Risk urgency
Answers
Suggested answer: A

Which of the following Process Groups covers all nine Project Management Knowledge Areas?

A.
Executing
A.
Executing
Answers
B.
Monitoring and Controlling
B.
Monitoring and Controlling
Answers
C.
Planning
C.
Planning
Answers
D.
Initiating
D.
Initiating
Answers
Suggested answer: C

The process of identifying the stakeholders' information needs is completed during:

A.
Plan Communications.
A.
Plan Communications.
Answers
B.
Manage Stakeholder Expectations.
B.
Manage Stakeholder Expectations.
Answers
C.
Stakeholder Analysis.
C.
Stakeholder Analysis.
Answers
D.
Identify Stakeholders.
D.
Identify Stakeholders.
Answers
Suggested answer: A

What is the most accurate rough order of magnitude (ROM)?

A.
In the Initiation phase, the estimate is in the range of +/- 50%.
A.
In the Initiation phase, the estimate is in the range of +/- 50%.
Answers
B.
In the Planning phase, the estimate is in the range of +/- 50%.
B.
In the Planning phase, the estimate is in the range of +/- 50%.
Answers
C.
In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%.
C.
In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%.
Answers
D.
In the Closing phase, the estimate is in the range of +/- 15%.
D.
In the Closing phase, the estimate is in the range of +/- 15%.
Answers
Suggested answer: A

Project contracts generally fall into which of the following three broad categories?

A.
Fixed-price, cost reimbursable, time and materials
A.
Fixed-price, cost reimbursable, time and materials
Answers
B.
Make-or-buy, margin analysis, fixed-price
B.
Make-or-buy, margin analysis, fixed-price
Answers
C.
Time and materials, fixed-price, margin analysis
C.
Time and materials, fixed-price, margin analysis
Answers
D.
Make-or-buy, lump-sum, cost-plus-incentive
D.
Make-or-buy, lump-sum, cost-plus-incentive
Answers
Suggested answer: A

Which of the following events would result in a baseline update?

A.
A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.
A.
A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.
Answers
B.
A customer has approved a change request broadening the project scope and increasing the budget.
B.
A customer has approved a change request broadening the project scope and increasing the budget.
Answers
C.
One of the risks identified in the risk management plan occurs, resulting in a schedule delay.
C.
One of the risks identified in the risk management plan occurs, resulting in a schedule delay.
Answers
D.
One of the key project team resources has left the team and no replacement is available.
D.
One of the key project team resources has left the team and no replacement is available.
Answers
Suggested answer: B

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

A.
Applying calendars
A.
Applying calendars
Answers
B.
Resource leveling
B.
Resource leveling
Answers
C.
Resource planning
C.
Resource planning
Answers
D.
Resource conflict management
D.
Resource conflict management
Answers
Suggested answer: B

"Tailoring" is defined as the:

A.
effort of addressing each process to determine which are appropriate and their appropriate degree of rigor.
A.
effort of addressing each process to determine which are appropriate and their appropriate degree of rigor.
Answers
B.
act of creating a project team with the specialized skills required to produce a required product or service.
B.
act of creating a project team with the specialized skills required to produce a required product or service.
Answers
C.
action taken to bring a defective or nonconforming component into compliance with requirements or specifications.
C.
action taken to bring a defective or nonconforming component into compliance with requirements or specifications.
Answers
D.
adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scope.
D.
adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scope.
Answers
Suggested answer: A

Which is an input to the Verify Scope process?

A.
Performance report
A.
Performance report
Answers
B.
Work breakdown structure (WBS)
B.
Work breakdown structure (WBS)
Answers
C.
Requested changes
C.
Requested changes
Answers
D.
Project management plan
D.
Project management plan
Answers
Suggested answer: D

Which is an output from Distribute Information?

A.
Earned value analysis
A.
Earned value analysis
Answers
B.
Trend analysis
B.
Trend analysis
Answers
C.
Project records
C.
Project records
Answers
D.
Performance reviews
D.
Performance reviews
Answers
Suggested answer: C

Explanation:

Topic 5, Volume E

Total 908 questions
Go to page: of 91