PMI CAPM Practice Test - Questions Answers, Page 61
List of questions
Question 601
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
Question 602
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?
Question 603
Which of the following is a strategy to deal with positive risks or opportunities?
Question 604
What are the identified risks for doing excessive decomposition in a WBS?
Question 605
Which statement is true about the project management body of knowledge?
Question 606
The initial development of a Project Scope Management plan uses which technique?
Question 607
Which of the following is a project constraint?
Question 608
An input to the Estimate Activity Resources process is:
Question 609
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000.
What is the cost performance index?
Question 610
Which technique is utilized in the Control Schedule process?
Question