Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

A.
The risk of achieving the shortened project time is increased.
A.
The risk of achieving the shortened project time is increased.
Answers
B.
The critical path will have positive total float.
B.
The critical path will have positive total float.
Answers
C.
Contingency reserves are released for redeployment by the project manager.
C.
Contingency reserves are released for redeployment by the project manager.
Answers
D.
Duration buffers are added to maintain a focus on planned activity durations.
D.
Duration buffers are added to maintain a focus on planned activity durations.
Answers
Suggested answer: A

Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?

A.
Control Scope
A.
Control Scope
Answers
B.
Collect Requirements
B.
Collect Requirements
Answers
C.
Create WBS
C.
Create WBS
Answers
D.
Define Scope
D.
Define Scope
Answers
Suggested answer: B

Which of the following is a strategy to deal with positive risks or opportunities?

A.
Mitigate
A.
Mitigate
Answers
B.
Transfer
B.
Transfer
Answers
C.
Exploit
C.
Exploit
Answers
D.
Avoid
D.
Avoid
Answers
Suggested answer: C

What are the identified risks for doing excessive decomposition in a WBS?

A.
Insufficient project funding and disqualification of sellers
A.
Insufficient project funding and disqualification of sellers
Answers
B.
Insufficient project funding and ineffective use of resources
B.
Insufficient project funding and ineffective use of resources
Answers
C.
Disqualification of sellers and non-productive management efforts
C.
Disqualification of sellers and non-productive management efforts
Answers
D.
Non-productive management effort and inefficient use of resources
D.
Non-productive management effort and inefficient use of resources
Answers
Suggested answer: D

Which statement is true about the project management body of knowledge?

A.
Recognized by every project manager
A.
Recognized by every project manager
Answers
B.
Constantly evolving
B.
Constantly evolving
Answers
C.
The sum of all knowledge related to project management
C.
The sum of all knowledge related to project management
Answers
D.
A sum of knowledge that should be applied on every project
D.
A sum of knowledge that should be applied on every project
Answers
Suggested answer: B

The initial development of a Project Scope Management plan uses which technique?

A.
Alternatives identification
A.
Alternatives identification
Answers
B.
Scope decomposition
B.
Scope decomposition
Answers
C.
Expert judgment
C.
Expert judgment
Answers
D.
Product analysis
D.
Product analysis
Answers
Suggested answer: C

Which of the following is a project constraint?

A.
Twenty-five percent staff turnover is expected.
A.
Twenty-five percent staff turnover is expected.
Answers
B.
The technology to be used is cutting-edge.
B.
The technology to be used is cutting-edge.
Answers
C.
Project leadership may change due to volatile political environment.
C.
Project leadership may change due to volatile political environment.
Answers
D.
The product is needed in 250 days.
D.
The product is needed in 250 days.
Answers
Suggested answer: D

An input to the Estimate Activity Resources process is:

A.
Activity resource requirements.
A.
Activity resource requirements.
Answers
B.
Published estimating data.
B.
Published estimating data.
Answers
C.
Resource calendars.
C.
Resource calendars.
Answers
D.
Resource breakdown structure (RBS).
D.
Resource breakdown structure (RBS).
Answers
Suggested answer: C

The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000.

What is the cost performance index?

A.
0.8
A.
0.8
Answers
B.
0.89
B.
0.89
Answers
C.
1.13
C.
1.13
Answers
D.
1.25
D.
1.25
Answers
Suggested answer: A

Which technique is utilized in the Control Schedule process?

A.
Performance measure
A.
Performance measure
Answers
B.
Baseline schedule
B.
Baseline schedule
Answers
C.
Schedule network analysis
C.
Schedule network analysis
Answers
D.
Variance analysis
D.
Variance analysis
Answers
Suggested answer: D