PMI CAPM Practice Test - Questions Answers, Page 61
List of questions
Related questions
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?
Which of the following is a strategy to deal with positive risks or opportunities?
What are the identified risks for doing excessive decomposition in a WBS?
Which statement is true about the project management body of knowledge?
The initial development of a Project Scope Management plan uses which technique?
Which of the following is a project constraint?
An input to the Estimate Activity Resources process is:
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000.
What is the cost performance index?
Which technique is utilized in the Control Schedule process?
Question