PMI CAPM Practice Test - Questions Answers, Page 63
List of questions
Question 621
Projects are separated into phases or subprojects; these phases include:
Question 622
In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?
Question 623
Which of the following is an input to the Develop Project Charter process?
Question 624
The diagram below is an example of a:
Question 625
Who is responsible for initiating a project?
Question 626
Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?
Question 627
Activity cost estimates are quantitative assessments of the probable costs required to:
Question 628
The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:
Question 629
How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?
Question 630
The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?
Question