ExamGecko
Home Home / PMI / CAPM

PMI CAPM Practice Test - Questions Answers, Page 64

Question list
Search
Search

Who determines which dependencies are mandatory during the Sequence Activities process?

A.
Project manager
A.
Project manager
Answers
B.
External stakeholders
B.
External stakeholders
Answers
C.
Internal stakeholders
C.
Internal stakeholders
Answers
D.
Project team
D.
Project team
Answers
Suggested answer: D

Risk exists the moment that a project is:

A.
planned.
A.
planned.
Answers
B.
conceived.
B.
conceived.
Answers
C.
chartered.
C.
chartered.
Answers
D.
executed.
D.
executed.
Answers
Suggested answer: B

Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?

A.
Cost Plus Award Fee Contract (CPAF)
A.
Cost Plus Award Fee Contract (CPAF)
Answers
B.
Firm-Fixed -Price Contract (FFP)
B.
Firm-Fixed -Price Contract (FFP)
Answers
C.
Time and Material Contract (T&M)
C.
Time and Material Contract (T&M)
Answers
D.
Cost Plus Incentive Fee Contract (CPIF)
D.
Cost Plus Incentive Fee Contract (CPIF)
Answers
Suggested answer: C

Which characteristics do effective project managers possess?

A.
Project management knowledge, performance skills, and personal effectiveness
A.
Project management knowledge, performance skills, and personal effectiveness
Answers
B.
Preparedness, project management knowledge, and personality characteristics
B.
Preparedness, project management knowledge, and personality characteristics
Answers
C.
General management, preparedness, and project management knowledge
C.
General management, preparedness, and project management knowledge
Answers
D.
Assertiveness, collaboration, and performance skills
D.
Assertiveness, collaboration, and performance skills
Answers
Suggested answer: A

In the basic communication model, which term refers to the method that is used to convey the message?

A.
Decode
A.
Decode
Answers
B.
Encode
B.
Encode
Answers
C.
Medium
C.
Medium
Answers
D.
Noise
D.
Noise
Answers
Suggested answer: C

During project selection, which factor is most important?

A.
Types of constraints
A.
Types of constraints
Answers
B.
Internal business needs
B.
Internal business needs
Answers
C.
Budget
C.
Budget
Answers
D.
Schedule
D.
Schedule
Answers
Suggested answer: B

The staffing management plan is part of the:

A.
organizational process assets.
A.
organizational process assets.
Answers
B.
resource calendar.
B.
resource calendar.
Answers
C.
human resource plan.
C.
human resource plan.
Answers
D.
Develop Project Team process.
D.
Develop Project Team process.
Answers
Suggested answer: C

Which is an output of the Collect Requirements process?

A.
Requirements traceability matrix
A.
Requirements traceability matrix
Answers
B.
Project scope statement
B.
Project scope statement
Answers
C.
WBS dictionary
C.
WBS dictionary
Answers
D.
Work performance measurements
D.
Work performance measurements
Answers
Suggested answer: A

Which activity may occur at project or phase closure?

A.
Acceptance of deliverables
A.
Acceptance of deliverables
Answers
B.
Change requests
B.
Change requests
Answers
C.
Project management plan updates
C.
Project management plan updates
Answers
D.
Benchmarking
D.
Benchmarking
Answers
Suggested answer: A

Which of the following is an input to Direct and Manage Project Execution?

A.
Performance reports
A.
Performance reports
Answers
B.
Project charter
B.
Project charter
Answers
C.
Outputs from planning processes
C.
Outputs from planning processes
Answers
D.
Enterprise environmental factors
D.
Enterprise environmental factors
Answers
Suggested answer: D
Total 908 questions