Who determines which dependencies are mandatory during the Sequence Activities process?
A.
Project manager
B.
External stakeholders
C.
Internal stakeholders
D.
Project team
Risk exists the moment that a project is:
A.
planned.
B.
conceived.
C.
chartered.
D.
executed.
Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?
A.
Cost Plus Award Fee Contract (CPAF)
B.
Firm-Fixed -Price Contract (FFP)
C.
Time and Material Contract (T&M)
D.
Cost Plus Incentive Fee Contract (CPIF)
Which characteristics do effective project managers possess?
A.
Project management knowledge, performance skills, and personal effectiveness
B.
Preparedness, project management knowledge, and personality characteristics
C.
General management, preparedness, and project management knowledge
D.
Assertiveness, collaboration, and performance skills
In the basic communication model, which term refers to the method that is used to convey the message?
A.
Decode
B.
Encode
C.
Medium
D.
Noise
During project selection, which factor is most important?
A.
Types of constraints
B.
Internal business needs
C.
Budget
D.
Schedule
The staffing management plan is part of the:
A.
organizational process assets.
B.
resource calendar.
C.
human resource plan.
D.
Develop Project Team process.
Which is an output of the Collect Requirements process?
A.
Requirements traceability matrix
B.
Project scope statement
C.
WBS dictionary
D.
Work performance measurements
Which activity may occur at project or phase closure?
A.
Acceptance of deliverables
B.
Change requests
C.
Project management plan updates
D.
Benchmarking
Which of the following is an input to Direct and Manage Project Execution?
A.
Performance reports
B.
Project charter
C.
Outputs from planning processes
D.
Enterprise environmental factors