ExamGecko
Home Home / PMI / CAPM

PMI CAPM Practice Test - Questions Answers, Page 66

Question list
Search
Search

Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

A.
Scope baseline
A.
Scope baseline
Answers
B.
Scope management plan
B.
Scope management plan
Answers
C.
Change management plan
C.
Change management plan
Answers
D.
Cost baseline
D.
Cost baseline
Answers
Suggested answer: A

Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

A.
Variance Analysis
A.
Variance Analysis
Answers
B.
Define Scope
B.
Define Scope
Answers
C.
Verify Scope
C.
Verify Scope
Answers
D.
Control Scope
D.
Control Scope
Answers
Suggested answer: D

The total of the planned value (PV) is also known as:

A.
work breakdown structure (WBS).
A.
work breakdown structure (WBS).
Answers
B.
schedule target.
B.
schedule target.
Answers
C.
performance measurement baseline (PMB).
C.
performance measurement baseline (PMB).
Answers
D.
earned value baseline.
D.
earned value baseline.
Answers
Suggested answer: C

When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

A.
event.
A.
event.
Answers
B.
response,
B.
response,
Answers
C.
perception.
C.
perception.
Answers
D.
impact.
D.
impact.
Answers
Suggested answer: A

Plan-do-check-act is also known as:

A.
prevention over inspection.
A.
prevention over inspection.
Answers
B.
statistical sampling.
B.
statistical sampling.
Answers
C.
management responsibility,
C.
management responsibility,
Answers
D.
continuous improvement.
D.
continuous improvement.
Answers
Suggested answer: D

Which of the following is a tool or technique used in the Determine Budget process?

A.
Variance analysis
A.
Variance analysis
Answers
B.
Three-point estimating
B.
Three-point estimating
Answers
C.
Bottom-up estimating
C.
Bottom-up estimating
Answers
D.
Historical relationships
D.
Historical relationships
Answers
Suggested answer: D

The risk shared between the buyer and seller is determined by the:

A.
assumption log.
A.
assumption log.
Answers
B.
quality checklist.
B.
quality checklist.
Answers
C.
risk register.
C.
risk register.
Answers
D.
contract type.
D.
contract type.
Answers
Suggested answer: D

The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:

A.
operate separately.
A.
operate separately.
Answers
B.
move together in batches,
B.
move together in batches,
Answers
C.
overlap and interact.
C.
overlap and interact.
Answers
D.
move in a sequence.
D.
move in a sequence.
Answers
Suggested answer: C

The process for performing variance analysis may vary, depending on:

A.
scenario building, technology forecasting, and forecast by analogy.
A.
scenario building, technology forecasting, and forecast by analogy.
Answers
B.
working relationships among various stakeholders and team members.
B.
working relationships among various stakeholders and team members.
Answers
C.
application area, the standard used, and the industry,
C.
application area, the standard used, and the industry,
Answers
D.
work to be completed next.
D.
work to be completed next.
Answers
Suggested answer: C

A tool and technique used during the Define Scope process is:

A.
facilitated workshops.
A.
facilitated workshops.
Answers
B.
observations.
B.
observations.
Answers
C.
questionnaires and surveys.
C.
questionnaires and surveys.
Answers
D.
group creativity techniques.
D.
group creativity techniques.
Answers
Suggested answer: A
Total 908 questions
Go to page: of 91