Which type of risk diagram is useful for showing time ordering of events?

A.
Ishikawa
A.
Ishikawa
Answers
B.
Milestone
B.
Milestone
Answers
C.
Influence
C.
Influence
Answers
D.
Decision tree
D.
Decision tree
Answers
Suggested answer: C

In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

A.
Start-to-start (SS)
A.
Start-to-start (SS)
Answers
B.
Start-to-finish (SF)
B.
Start-to-finish (SF)
Answers
C.
Rnish-to-finish (FF)
C.
Rnish-to-finish (FF)
Answers
D.
Finish-to-start (FS)
D.
Finish-to-start (FS)
Answers
Suggested answer: D

A required input for Create WBS is a project:

A.
quality plan.
A.
quality plan.
Answers
B.
schedule network.
B.
schedule network.
Answers
C.
management document update.
C.
management document update.
Answers
D.
scope statement.
D.
scope statement.
Answers
Suggested answer: D

Which of the following statements is true regarding project and product lifecycles?

A.
A single product lifecycle may consist of multiple project lifecycles.
A.
A single product lifecycle may consist of multiple project lifecycles.
Answers
B.
A product lifecycle is always shorter than the project lifecycle.
B.
A product lifecycle is always shorter than the project lifecycle.
Answers
C.
A single product lifecycle can only have one project lifecycle.
C.
A single product lifecycle can only have one project lifecycle.
Answers
D.
A single project lifecycle may consist of multiple product lifecycles.
D.
A single project lifecycle may consist of multiple product lifecycles.
Answers
Suggested answer: A

Which tool or technique is used in Close Procurements?

A.
Contract plan
A.
Contract plan
Answers
B.
Procurement plan
B.
Procurement plan
Answers
C.
Closure process
C.
Closure process
Answers
D.
Procurement audits
D.
Procurement audits
Answers
Suggested answer: D

Which of the following is an output of Direct and Manage Project Execution?

A.
Project management plan
A.
Project management plan
Answers
B.
Change request status updates
B.
Change request status updates
Answers
C.
Organizational process assets updates
C.
Organizational process assets updates
Answers
D.
Work performance information
D.
Work performance information
Answers
Suggested answer: D

Which of the following is an input to Develop Human Resource Plan?

A.
Team performance assessment
A.
Team performance assessment
Answers
B.
Roles and responsibilities
B.
Roles and responsibilities
Answers
C.
Staffing management plan
C.
Staffing management plan
Answers
D.
Enterprise environmental factors
D.
Enterprise environmental factors
Answers
Suggested answer: D

Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?

A.
Performance organizations
A.
Performance organizations
Answers
B.
Schedule baselines
B.
Schedule baselines
Answers
C.
Work performance measurements
C.
Work performance measurements
Answers
D.
Change requests
D.
Change requests
Answers
Suggested answer: C

Testing falls into which of the following categories of cost of quality?

A.
Internal failure costs
A.
Internal failure costs
Answers
B.
Prevention costs
B.
Prevention costs
Answers
C.
Appraisal costs
C.
Appraisal costs
Answers
D.
External failure costs
D.
External failure costs
Answers
Suggested answer: C

Another name for an Ishikawa diagram is:

A.
cause and effect diagram.
A.
cause and effect diagram.
Answers
B.
control chart.
B.
control chart.
Answers
C.
flowchart.
C.
flowchart.
Answers
D.
histogram.
D.
histogram.
Answers
Suggested answer: A