The key benefit of the Monitoring and Controlling Process Group is the ability to:

A.
establish and manage project communication channels, both external and internal to the project team.
A.
establish and manage project communication channels, both external and internal to the project team.
Answers
B.
influence the stakeholders that want to circumvent integrated change control so that their changes are implemented.
B.
influence the stakeholders that want to circumvent integrated change control so that their changes are implemented.
Answers
C.
monitor the ongoing project team against the team performance assessments and the project performance baseline.
C.
monitor the ongoing project team against the team performance assessments and the project performance baseline.
Answers
D.
observe and measure project performance regularly and consistently to identify variances from the project management plan.
D.
observe and measure project performance regularly and consistently to identify variances from the project management plan.
Answers
Suggested answer: D

Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?

A.
Project Plan
A.
Project Plan
Answers
B.
Responsibility Matrix
B.
Responsibility Matrix
Answers
C.
Issue Log
C.
Issue Log
Answers
D.
Scope Document
D.
Scope Document
Answers
Suggested answer: C

Who provides the inputs for the original estimates of activity durations for tasks on the project plan?

A.
Project sponsor
A.
Project sponsor
Answers
B.
Project manager
B.
Project manager
Answers
C.
Person responsible for project scheduling
C.
Person responsible for project scheduling
Answers
D.
Person who is most familiar with the task
D.
Person who is most familiar with the task
Answers
Suggested answer: D

Which of the following is the primary output of the Identify Risks process?

A.
Risk management plan
A.
Risk management plan
Answers
B.
Risk register
B.
Risk register
Answers
C.
Change requests
C.
Change requests
Answers
D.
Risk response plan
D.
Risk response plan
Answers
Suggested answer: B

Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?

A.
Cyclic
A.
Cyclic
Answers
B.
Progressive
B.
Progressive
Answers
C.
Repetitive
C.
Repetitive
Answers
D.
Iterative
D.
Iterative
Answers
Suggested answer: B

Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?

A.
Requirements traceability matrix
A.
Requirements traceability matrix
Answers
B.
Work breakdown structure (WBS) dictionary
B.
Work breakdown structure (WBS) dictionary
Answers
C.
Requirements management plan
C.
Requirements management plan
Answers
D.
Requirements documentation
D.
Requirements documentation
Answers
Suggested answer: A

Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?

A.
Cost-reimbursable contracts
A.
Cost-reimbursable contracts
Answers
B.
Time and Material contracts (T&M)
B.
Time and Material contracts (T&M)
Answers
C.
Fixed-price contracts
C.
Fixed-price contracts
Answers
D.
Cost Plus Fixed Fee Contracts (CPFF)
D.
Cost Plus Fixed Fee Contracts (CPFF)
Answers
Suggested answer: C

Types of internal failure costs include:

A.
inspections.
A.
inspections.
Answers
B.
equipment and training.
B.
equipment and training.
Answers
C.
lost business.
C.
lost business.
Answers
D.
reworking and scrapping.
D.
reworking and scrapping.
Answers
Suggested answer: D

In a weak matrix, the project managers role is:

A.
part-time
A.
part-time
Answers
B.
full-time
B.
full-time
Answers
C.
occasional
C.
occasional
Answers
D.
unlimited
D.
unlimited
Answers
Suggested answer: A

Which of the following is an example of schedule compression?

A.
Activity sequencing
A.
Activity sequencing
Answers
B.
Resource leveling
B.
Resource leveling
Answers
C.
Lead and lag adjusting
C.
Lead and lag adjusting
Answers
D.
Crashing
D.
Crashing
Answers
Suggested answer: D
Total 908 questions