ExamGecko
Home Home / PMI / CAPM

PMI CAPM Practice Test - Questions Answers, Page 55

Question list
Search
Search

Which is the correct formula for calculating expected activity cost for three-point estimating?

A.
Ce = (C0 + 6Cm + Cp)/4
A.
Ce = (C0 + 6Cm + Cp)/4
Answers
B.
Ce = (6C0 + Cm + Cp)/4
B.
Ce = (6C0 + Cm + Cp)/4
Answers
C.
Ce = (C0 + 4Cm + Cp)/6D. Ce = (C0 + CД, + 4Cp) / 6
C.
Ce = (C0 + 4Cm + Cp)/6D. Ce = (C0 + CД, + 4Cp) / 6
Answers
Suggested answer: C

Monte Carlo is which type of risk analysis technique?

A.
Probability
A.
Probability
Answers
B.
Quantitative
B.
Quantitative
Answers
C.
Qualitative
C.
Qualitative
Answers
D.
Sensitivity
D.
Sensitivity
Answers
Suggested answer: B

When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?

A.
Authority
A.
Authority
Answers
B.
Role
B.
Role
Answers
C.
Competency
C.
Competency
Answers
D.
Responsibility
D.
Responsibility
Answers
Suggested answer: C

Which of the following reduces the probability of potential consequences of project risk events?

A.
Preventive action
A.
Preventive action
Answers
B.
Risk management
B.
Risk management
Answers
C.
Corrective action
C.
Corrective action
Answers
D.
Defect repair
D.
Defect repair
Answers
Suggested answer: A

The project manager needs to review the templates in use. The templates are part of the:

A.
Enterprise environmental factors.
A.
Enterprise environmental factors.
Answers
B.
Historical information,
B.
Historical information,
Answers
C.
Organizational process assets.
C.
Organizational process assets.
Answers
D.
Corporate knowledge base.
D.
Corporate knowledge base.
Answers
Suggested answer: C

Which of the following Project Communication Management processes uses performance reports as an input?

A.
Manage Stakeholder Expectations
A.
Manage Stakeholder Expectations
Answers
B.
Report Performance
B.
Report Performance
Answers
C.
Distribute Information
C.
Distribute Information
Answers
D.
Plan Communications
D.
Plan Communications
Answers
Suggested answer: C

Which cost estimate technique includes contingencies to account for cost uncertainty?

A.
Vendor bid analysis
A.
Vendor bid analysis
Answers
B.
Three-point estimates
B.
Three-point estimates
Answers
C.
Parametric estimating
C.
Parametric estimating
Answers
D.
Reserve analysis
D.
Reserve analysis
Answers
Suggested answer: D

Which of the following is an output of the Perform Integrated Change Control process?

A.
Project document updates
A.
Project document updates
Answers
B.
Organizational process assets updates
B.
Organizational process assets updates
Answers
C.
Change requests
C.
Change requests
Answers
D.
Deliverables
D.
Deliverables
Answers
Suggested answer: A

Which of the following is an input to Control Scope?

A.
Project schedule
A.
Project schedule
Answers
B.
Organizational process assets updates
B.
Organizational process assets updates
Answers
C.
Project document updates
C.
Project document updates
Answers
D.
Work performance information
D.
Work performance information
Answers
Suggested answer: D

Lessons learned documentation is gathered during which of the following Project Management Process Groups?

A.
Planning
A.
Planning
Answers
B.
Executing
B.
Executing
Answers
C.
Closing
C.
Closing
Answers
D.
Initiating
D.
Initiating
Answers
Suggested answer: C