PMI CAPM Practice Test - Questions Answers, Page 57
List of questions
Question 561
Which of the following types of a dependency determination is used to define the sequence of activities?
Question 562
Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?
Question 563
Co-location is a tool and technique of:
Question 564
During which process would stakeholders provide formal acceptance of the completed project scope?
Question 565
The PV is $1000, EV is $2000, and AC is $1500. What is CPI?
Question 566
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
Question 567
What is the primary benefit of meeting quality requirements?
Question 568
What is a tool to improve team performance?
Question 569
Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?
Question 570
Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?
Question