ExamGecko
Home Home / PMI / CAPM

PMI CAPM Practice Test - Questions Answers, Page 69

Question list
Search
Search

Which baselines make up the performance measurement baseline?

A.
Scope baseline, cost baseline, and schedule baseline
A.
Scope baseline, cost baseline, and schedule baseline
Answers
B.
Scope baseline, project management baseline, and quality baseline
B.
Scope baseline, project management baseline, and quality baseline
Answers
C.
Cost baseline, schedule baseline, and risk baseline
C.
Cost baseline, schedule baseline, and risk baseline
Answers
D.
Cost baseline, project management baseline, and schedule baseline
D.
Cost baseline, project management baseline, and schedule baseline
Answers
Suggested answer: A

The application of knowledge, skills, tools, and techniques to project activities to meet project requirements describes management of which of the following?

A.
Project
A.
Project
Answers
B.
Scope
B.
Scope
Answers
C.
Contract
C.
Contract
Answers
D.
Program
D.
Program
Answers
Suggested answer: A

Prototype development may be used as a tool for which of the following risk response strategies?

A.
Avoid
A.
Avoid
Answers
B.
Accept
B.
Accept
Answers
C.
Mitigate
C.
Mitigate
Answers
D.
Exploit
D.
Exploit
Answers
Suggested answer: C

Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?

A.
Estimate at completion
A.
Estimate at completion
Answers
B.
Cost performance
B.
Cost performance
Answers
C.
Schedule performance
C.
Schedule performance
Answers
D.
To-complete performance
D.
To-complete performance
Answers
Suggested answer: D

A tool and technique used during the Collect Requirements process is:

A.
prototypes.
A.
prototypes.
Answers
B.
expert judgment.
B.
expert judgment.
Answers
C.
alternatives identification.
C.
alternatives identification.
Answers
D.
product analysis.
D.
product analysis.
Answers
Suggested answer: A

One of the objectives of a quality audit is to:

A.
highlight the need for root cause analysis.
A.
highlight the need for root cause analysis.
Answers
B.
share the process documentation among stakeholders.
B.
share the process documentation among stakeholders.
Answers
C.
offer assistance with non-value-added activities.
C.
offer assistance with non-value-added activities.
Answers
D.
identify all of the gaps or shortcomings.
D.
identify all of the gaps or shortcomings.
Answers
Suggested answer: D

While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?

A.
Communications management plan
A.
Communications management plan
Answers
B.
Human resource plan
B.
Human resource plan
Answers
C.
Quality management plan
C.
Quality management plan
Answers
D.
Procurement management plan
D.
Procurement management plan
Answers
Suggested answer: A

Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?

A.
Acquisition
A.
Acquisition
Answers
B.
Negotiation
B.
Negotiation
Answers
C.
Virtual team
C.
Virtual team
Answers
D.
Pre-assignment
D.
Pre-assignment
Answers
Suggested answer: D

Which of the following is a group decision-making technique?

A.
Brainstorming
A.
Brainstorming
Answers
B.
Focus groups
B.
Focus groups
Answers
C.
Affinity diagram
C.
Affinity diagram
Answers
D.
Plurality
D.
Plurality
Answers
Suggested answer: D

Which statement correctly describes the value of a business case?

A.
It provides the necessary information to determine if a project is worth the required investment.
A.
It provides the necessary information to determine if a project is worth the required investment.
Answers
B.
It provides for alternative dispute resolution procedures in event of contract default.
B.
It provides for alternative dispute resolution procedures in event of contract default.
Answers
C.
It offers one of several alternative scenarios which assist in performing qualitative risk analysis.
C.
It offers one of several alternative scenarios which assist in performing qualitative risk analysis.
Answers
D.
It is used to help a project manager understand the scope of commercial advantages.
D.
It is used to help a project manager understand the scope of commercial advantages.
Answers
Suggested answer: A
Total 908 questions
Go to page: of 91