The project manager is working in the processes of Project Resource Management. Which process is the project manager developing if they are using parametric estimation?

A.
Plan Resource Management
A.
Plan Resource Management
Answers
B.
Estimate Activity Resources
B.
Estimate Activity Resources
Answers
C.
Estimate Costs
C.
Estimate Costs
Answers
D.
Acquire Resources
D.
Acquire Resources
Answers
Suggested answer: B

Which is the tool or technique that is used to obtain the list of activities from the work packages?

A.
Data analysis
A.
Data analysis
Answers
B.
Leads and lags
B.
Leads and lags
Answers
C.
Precedence diagramming method
C.
Precedence diagramming method
Answers
D.
Decomposition
D.
Decomposition
Answers
Suggested answer: D

Which project manager competency is displayed through the knowledge, skills, and behaviors related to specific domains of project, program, and portfolio management?

A.
Leadership management
A.
Leadership management
Answers
B.
Technical project management
B.
Technical project management
Answers
C.
Strategic management
C.
Strategic management
Answers
D.
Business management
D.
Business management
Answers
Suggested answer: B

What are the objectives of Initiation processes?

A.
Initiation processes are performed in order to develop the project charier and Identify stakeholders.
A.
Initiation processes are performed in order to develop the project charier and Identify stakeholders.
Answers
B.
Initiation processes are performed in order to obtain budget approval for a project or phase and approve scope with customers.
B.
Initiation processes are performed in order to obtain budget approval for a project or phase and approve scope with customers.
Answers
C.
Initiation processes are performed to identify business objectives for a project or phase and identify stakeholders' goals.
C.
Initiation processes are performed to identify business objectives for a project or phase and identify stakeholders' goals.
Answers
D.
Initiation processes are performed to map initial requirements for a project or phase and prioritize them with stakeholders.
D.
Initiation processes are performed to map initial requirements for a project or phase and prioritize them with stakeholders.
Answers
Suggested answer: D

A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?

A.
What-if scenario analysis
A.
What-if scenario analysis
Answers
B.
Simulation
B.
Simulation
Answers
C.
Alternatives analysis
C.
Alternatives analysis
Answers
D.
Reserve analysis
D.
Reserve analysis
Answers
Suggested answer: D

A project manager held a meeting and listed all team members' ideas for improving the product on a white board. What data gathering technique did the project manager apply?

A.
Focus groups
A.
Focus groups
Answers
B.
Interviews
B.
Interviews
Answers
C.
Brainstorming
C.
Brainstorming
Answers
D.
Delphi technique
D.
Delphi technique
Answers
Suggested answer: C

What is the best tool to calculate the critical path on a project?

A.
Critical chain method
A.
Critical chain method
Answers
B.
Graphical evaluation and review technique (GERT) diagram
B.
Graphical evaluation and review technique (GERT) diagram
Answers
C.
Gantt chart
C.
Gantt chart
Answers
D.
Project network diagram
D.
Project network diagram
Answers
Suggested answer: C

A project has an estimated duration of 10 months with a total budget of US$220,000. At the end of the fifth month, it is estimated that at completion, the project will incur US$250,000. If the actual cost (AC) calculated is US$150,000, what is the earned value (EV) of the project?

A.
USS-30,000
A.
USS-30,000
Answers
B.
US$120,000
B.
US$120,000
Answers
C.
US$370,000
C.
US$370,000
Answers
D.
US$400,000
D.
US$400,000
Answers
Suggested answer: D

Which components of the project management plan are inputs used when creating the stakeholder engagement plan?

A.
Risk, resource, and communications management plans
A.
Risk, resource, and communications management plans
Answers
B.
Scope, quality, and resource management plans
B.
Scope, quality, and resource management plans
Answers
C.
Procurement, integration, and risk management plans
C.
Procurement, integration, and risk management plans
Answers
D.
Communications, schedule, and cost management plans
D.
Communications, schedule, and cost management plans
Answers
Suggested answer: A

A project manager is identifying the risks of a project. Which technique should the project manager use?

A.
Representations of uncertainty
A.
Representations of uncertainty
Answers
B.
Prompt lists
B.
Prompt lists
Answers
C.
Audits
C.
Audits
Answers
D.
Risk categorization
D.
Risk categorization
Answers
Suggested answer: B