Which of the following is an example of facit knowledge?

A.
Risk register
A.
Risk register
Answers
B.
Project requirements
B.
Project requirements
Answers
C.
Expert judgment
C.
Expert judgment
Answers
D.
Make-or-buy analysis
D.
Make-or-buy analysis
Answers
Suggested answer: C

How can a project manager determine if the project activities comply with organizational and project policies, processes, and procedures?

A.
Look at the quality metrics.
A.
Look at the quality metrics.
Answers
B.
Validate the scope.
B.
Validate the scope.
Answers
C.
Review the quality checklist.
C.
Review the quality checklist.
Answers
D.
Conduct a quality audit.
D.
Conduct a quality audit.
Answers
Suggested answer: D

Company A has just been notified about a new legal requirement for its business operations. What is the classification of this item?

A.
Internal enterprise environmental factor
A.
Internal enterprise environmental factor
Answers
B.
Risk register database
B.
Risk register database
Answers
C.
External enterprise environmental factor
C.
External enterprise environmental factor
Answers
D.
Organizational process asset
D.
Organizational process asset
Answers
Suggested answer: C

In which sphere of influence is the project manager demonstrating the value of project management and advancing the efficacy of the project management office (PMO)?

A.
The organization
A.
The organization
Answers
B.
The project
B.
The project
Answers
C.
The industry
C.
The industry
Answers
D.
The product
D.
The product
Answers
Suggested answer: B

What should a project manager use to determine how much money is needed to complete a project?

A.
Earned value management (EVM)
A.
Earned value management (EVM)
Answers
B.
Estimate at completion (EAC)
B.
Estimate at completion (EAC)
Answers
C.
Earned value analysis (EVA)
C.
Earned value analysis (EVA)
Answers
D.
Budget at completion (BAG)
D.
Budget at completion (BAG)
Answers
Suggested answer: B

Creating the project scope statement is part of which process?

A.
Manage Scope
A.
Manage Scope
Answers
B.
Collect Requirements
B.
Collect Requirements
Answers
C.
Define Scope
C.
Define Scope
Answers
D.
Validate Scope
D.
Validate Scope
Answers
Suggested answer: C

A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs lo make this decision?

A.
Organizational process assets
A.
Organizational process assets
Answers
B.
Change management plan
B.
Change management plan
Answers
C.
Communications management plan
C.
Communications management plan
Answers
D.
Resource management plan
D.
Resource management plan
Answers
Suggested answer: C

What is a tool or technique used in the Control Quality process?

A.
Attribute sampling
A.
Attribute sampling
Answers
B.
Parametric estimating
B.
Parametric estimating
Answers
C.
Statistical sampling
C.
Statistical sampling
Answers
D.
Expert judgment
D.
Expert judgment
Answers
Suggested answer: A

What is the role of project management in terms of organizational strategy?

A.
Project management aligns initiatives, prioritizes work, and provides resources.
A.
Project management aligns initiatives, prioritizes work, and provides resources.
Answers
B.
Project management provides the strategic vision (or an organization lo achieve its goals.
B.
Project management provides the strategic vision (or an organization lo achieve its goals.
Answers
C.
Project management enables the achievement of organizational goals and objectives.
C.
Project management enables the achievement of organizational goals and objectives.
Answers
D.
Project management harmonizes components and controls interdependencies to realize specific benefits.
D.
Project management harmonizes components and controls interdependencies to realize specific benefits.
Answers
Suggested answer: C

Project reporting is a tool that is most closely associated with which process?

A.
Communicate Plan
A.
Communicate Plan
Answers
B.
Manage Communications
B.
Manage Communications
Answers
C.
Report Performance
C.
Report Performance
Answers
D.
Control Communications
D.
Control Communications
Answers
Suggested answer: B