ExamGecko
Home / IIBA / CCBA / List of questions
Ask Question

IIBA CCBA Practice Test - Questions Answers, Page 2

List of questions

Question 11

Report
Export
Collapse

Which of the following documents graphically depicts the project team members and displays their interrelationship for a specific project?

Project team directory
Project team directory
Project organization chart
Project organization chart
Project scope statement
Project scope statement
Project charter
Project charter
Suggested answer: B

Explanation:

Project organization chart is a document that graphically portrays the team members of the project and their interrelationships for a specific project. An organization chart is a diagram that shows the hierarchical structure of an organization. Usually a chart starts with a higher or superior level and branches downward to subordinate levels.

Answer D is incorrect. The project charter is the document that formally authorizes a project. The project charter provides the project manager with the authority to apply organizational resources to project activities. Answer A is incorrect. It is a documented list of project team members, their project roles, and communication information.

Answer C is incorrect. Project scope statement is the narrative description of the project scope. It includes major deliverables, project assumptions, project constraints, and a description of work. It helps developing a common understanding of project scope among the stakeholders. It is a documented description of the project to answer Questions such as What is being produced? How is it being produced? What is included? etc.

asked 18/09/2024
Parita Malbari
48 questions

Question 12

Report
Export
Collapse

What does MoSCoW mean when it comes to requirements prioritization?

Must, Should, Could, Would
Must, Should, Could, Would
Money, Schedule, Control, Waiting
Money, Schedule, Control, Waiting
Must, Should, Could, Won't
Must, Should, Could, Won't
Mustn't, Shouldn't, Couldn't, Won't
Mustn't, Shouldn't, Couldn't, Won't
Suggested answer: C

Explanation:

The MoSCoW Analysis approach allows requirements to filter into the four categories of must, should, could, won't.

Answer A is incorrect. This isn't the correct definition of MoSCow; the correct definition is must, should, could, won't.

Answer D is incorrect. This isn't the correct definition of MoSCow; the correct definition is must, should, could, won't.

Answer B is incorrect. This isn't the correct definition of MoSCow; the correct definition is must, should, could, won't.

asked 18/09/2024
Martijn Lammerts
43 questions

Question 13

Report
Export
Collapse

A business analyst is meeting with the customer of the project. The customer tells the business analyst that she can only allow the budget of $575,000 for the project. This budget is best described as what type of constraint?

Technical constraint
Technical constraint
Verified constraint
Verified constraint
Financial constraint
Financial constraint
Business constraint
Business constraint
Suggested answer: D

Explanation:

A business constraint describes the limitations on the available solution - including financial, schedule, and resource limitations.

Answer C is incorrect. Financial constraint is not a category of business analysis constraints and assumptions. Answer A is incorrect. A technical constraint describes an architectural decision that may affect the allowed solution, such as development language, hardware, or software.

Answer B is incorrect. There's not a category of constraints called a verified constraint.

asked 18/09/2024
John Ordonez
30 questions

Question 14

Report
Export
Collapse

You are the business analyst for your organization and you're working with Adam on business analysis processes. Adam allows the business analysis activities and resources to exist in support of the organization. Of the following, what type of business analysis stakeholder is Adam?

Project manager
Project manager
Domain subject matter expert
Domain subject matter expert
Sponsor
Sponsor
Regulator
Regulator
Suggested answer: C

Explanation:

Adam is the sponsor. The sponsor allows the business analysis activities and resources to exist in support of the organization.

Answer B is incorrect. The domain subject matter expert is a person who is steeped in knowledge regarding the project's purpose.

Answer A is incorrect. The project manager must ensure that the business analysis approach is compatible with other project activities.

Answer D is incorrect. The regulator approves any tailoring to the business analysis processes or activities.

asked 18/09/2024
Philippe Chretien
44 questions

Question 15

Report
Export
Collapse

A business analyst (BA) is tasked with performing a gap analysis between two existing systems to combine into a single system or run just one system. Which of the following modelling formats will show the requirements for both systems side by side?

Activity Flow
Activity Flow
Matrix
Matrix
Glossary
Glossary
Bubble Chart
Bubble Chart
Suggested answer: B
asked 18/09/2024
Xiaoyi Wu
38 questions

Question 16

Report
Export
Collapse

A Chief Information Officer (CIO) was discussing a solution approach for a technology project in a meeting where a business analyst (BA) was also present. Stakeholders were discussing advantages and disadvantages of each solution approach. What should be the top priority for the BA in assessing the solution approach?

The trade-off and value to stakeholder
The trade-off and value to stakeholder
The strategy alignment with the balanced scorecard
The strategy alignment with the balanced scorecard
The total cost of ownership of the project
The total cost of ownership of the project
The strategy design options
The strategy design options
Suggested answer: A
asked 18/09/2024
test fdf
47 questions

Question 17

Report
Export
Collapse

A business analyst (BA) has recently joined a large consultancy firm where BAs are globally distributed on different assignments. Where would the BA find expectations for business analysis work as mandated by the consultancy firm?

Organizational performance standards
Organizational performance standards
Information management approach
Information management approach
Modelling notations standards
Modelling notations standards
Business analysis approach
Business analysis approach
Suggested answer: D
asked 18/09/2024
tho nguyen
32 questions

Question 18

Report
Export
Collapse

A business analyst (BA) is assigned a new project and is beginning to prepare for elicitation. Which task must the BA complete before preparation of the elicitation process can begin?

Coordinate meeting logistics
Coordinate meeting logistics
Approve anticipated expenses
Approve anticipated expenses
Gather contact information of stakeholder
Gather contact information of stakeholder
Collect information on the business need
Collect information on the business need
Suggested answer: D
asked 18/09/2024
Frans Gafane
33 questions

Question 19

Report
Export
Collapse

An organization has hired a consulting firm to implement and customize a software solution they purchased. The firm has raised concerns regarding the effort required to develop a solution that meets all requirements. On what basis should the requirements be prioritized in this context?

Benefit
Benefit
Cost
Cost
Risk
Risk
Penalty
Penalty
Suggested answer: A
asked 18/09/2024
Paul Tierney
41 questions

Question 20

Report
Export
Collapse

A business analyst (BA) has elicited non-functional information for a system's replacement. In reviewing the elicitation results, the BA finds the number of concurrent users is a large portion of the target user group, which seems high. How should the BA proceed?

Observe a user performing the task to determine the length of time to complete the task
Observe a user performing the task to determine the length of time to complete the task
Document the elicitation results in the solution requirements specification then seek verification and validation in a requirements review
Document the elicitation results in the solution requirements specification then seek verification and validation in a requirements review
Conduct additional stakeholder analysis to determine whether any additional user groups were overlooked
Conduct additional stakeholder analysis to determine whether any additional user groups were overlooked
Confirm elicitation results by researching the actual concurrent users on the existing system and review findings with stakeholders
Confirm elicitation results by researching the actual concurrent users on the existing system and review findings with stakeholders
Suggested answer: D
asked 18/09/2024
Peter Takacs
28 questions
Total 516 questions
Go to page: of 52
Search

Related questions