IIBA CCBA Practice Test - Questions Answers, Page 10
List of questions
Related questions
Question 91
Your organization is using a plan-driven approach to business analysis. What must you do with all of the communication documents created as part of this high-priority project that you are serving as the business analyst for?
Explanation:
Communications in a plan-driven approach to business analysis must use formal communication.
Formal communications should be archived as part of the organizational process assets.
Answer A is incorrect. The communications management plan may dictate that the communications be archived, but this is not a requirement of the communications management plan.
Answer D is incorrect. The project manager may want to reference the communication but doesn't always need. If the communications are archived, then the project manager can access them as needed.
Answer B is incorrect. Communication documents are not destroyed; they are archived as part of the organizational process assets.
Question 92
Linda is the business analyst for her organization and she's working with Joe, a new business analyst, to prioritize requirements. Joe doesn't understand why requirements need to be prioritized; as all requirements are required, they should carry equal weight in the analysis. What should Linda tell Joe as to why requirements must be prioritized?
Explanation:
Prioritization of requirements is used to make certain that analysis and implementation efforts focus on the most critical requirements. The requirement prioritization process ranks the requirements by importance. It is a decision process. This process is used for determining the relative importance of requirements. These priorities determine which requirements should be targets for further analysis.
Answer C is incorrect. Requirements prioritization does not rank the requirements by the stakeholders, but by the needs of the stakeholders and the requirements that are most important to satisfy those needs.
Answer A is incorrect. Requirements prioritization does not rank the requirements according to the cost and schedule, but by importance.
Answer B is incorrect. Requirements prioritization does not rank the requirements on a weighted scale; this isn't a valid statement.
Question 93
What condition of the requirements must be fulfilled in order to use the matrix documentation approach to specify and model requirements?
Explanation:
In order to use the matrix documentation approach to model requirements, the identified requirements must have the uniform structure of their characteristics and identification.
Answer A is incorrect. The requirements do no need to have opposing values to use the matrix documentation approach.
Answer B is incorrect. While this choice is tempting, the best answer is the uniform structure.
Answer D is incorrect. This isn't a valid answer, as requirements don't need rated goals.
Question 94
Which of the following is a business management strategy originally developed by Motorola, USA in 1986?
Explanation:
Six Sigma is a business management strategy originally developed by Motorola, USA in 1986. It is widely used in many sectors of industry, although its use is not without controversy. The Six Sigma approach seeks to improve the quality of process outputs by identifying and removing the causes of defects (errors) and minimizing variability in manufacturing and business processes. It uses a set of quality management methods, including statistical methods, and creates a special infrastructure of people within the organization who are experts in these methods. Each Six Sigma project carried out within an organization follows a defined sequence of steps and has quantified financial targets.
Question 95
As a business analyst, you'll often have to coach stakeholders on the processes, knowledge areas, and tasks you'll complete for an organization. One of the knowledge areas is enterprise analysis. This knowledge area completes all of the following activities except for which one?
Explanation:
The Requirements Management and Communication knowledge area describes the activities and considerations to manage and express requirements to a broad and diverse audience. The execution of these tasks ensures the following facts:
The stakeholders have a shared understanding of the nature of a solution.
Those stakeholders with approval authority are in agreement as to the requirements that the solution shall meet.
Answer B, A, and C are incorrect. The Enterprise Analysis knowledge area describes the following business analysis activities:
It identifies business needs, problems, or opportunities. It defines the nature of a solution that meets that need.
It justifies the investment necessary to deliver that solution.
Question 96
You are the business analyst for your organization and you're working with your manager to discuss the constraints and assumptions that may affect the requirements. Your manager wants to know from where you've derived the list of constraints and assumptions. What's the best answer as to where assumptions and constraints are identified?
Explanation:
Assumptions and constraints are identified through elicitation from stakeholders.
Answer D is incorrect. Assumptions and constraints are not identified through document analysis.
Answer C is incorrect. Assumptions and constraints are not identified through risk identification, though false assumptions may be subject to risk analysis.
Answer A is incorrect. Assumptions and constraints are not identified through a review of project requirements.
Question 97
There are five tasks and six inputs to requirements management and communication. As a business analyst, you'll need to gather all of the following inputs for this knowledge area except for which one?
Explanation:
The work breakdown structure (WBS) is a tool used to define the scope of work and to develop estimates. This tool creates a hierarchy of work by decomposing the project scope into smaller and smaller pieces. WBS can perform the following tasks:
It may break the project into iterations, releases, or phases. It can break deliverables into work packages.
It may break activities into smaller tasks.
Answer C, A, and D are incorrect. The inputs to requirements management and communication are as follows:
Business Analysis (BA) communication plan Requirement Management Plan Solution Scope Requirements Structure Organizational Process Assets Stakeholder, List, Roles, and Responsibilities Requirements
Question 98
Which of the following is an output of the Identify Stakeholders process?
Explanation:
The Identify Stakeholders process identifies all people or organizations that are impacted by the project. It also documents relevant information regarding their interests, involvement, and impact on project success.
Stakeholder register and stakeholder management strategy are outputs of this process. Answer B is incorrect. Project charter is one of the inputs of the Identify Stakeholders process.
Answer A is incorrect. Scope baseline is one of the outputs of the Create Work Breakdown Structure (WBS) process.
Answer D is incorrect. Project scope statement is one of the outputs of the Define Scope process.
Question 99
You are documenting the requirements attribute for your requirements management plan. Which attribute would you use if you want to identify the person who created the requirements?
Explanation:
The author of the requirements is a good attribute to include in the requirements attribute. This allows follow- up Questions or clarifications, if necessary, for the project.
Answer A is incorrect. Absolute reference is needed to define specific requirements. A numeric coding is preferred over text and this code should not be reused.
Answer B is incorrect. The ownership attribute describes who will be the owner of the requirement or deliverable. The owner isn't necessarily the same person who created the requirement.
Answer C is incorrect. There is not an attribute called requirements sponsor, so this choice is not valid.
Question 100
A business analyst has just completed an elicitation event. What stakeholder(s) is/are involved in the documentation of the elicitation results?
Explanation:
Only the business analyst is involved in the documentation of the elicitation results.
Answer D is incorrect. Only the business analyst is involved in the documentation of the elicitation results, not the project manager and project sponsor.
Answer C is incorrect. Only the business analyst is involved in the documentation of the elicitation results, not the project manager and project team.
Answer A is incorrect. Only the business analyst is involved in the documentation of the elicitation results, not key stakeholders.
Question