Which stakeholder(s) will be involved to determine if the requirements can be implemented?

Domain subject matter expert
Domain subject matter expert
Implementation subject matter expert
Implementation subject matter expert
Project team members
Project team members
Sponsor
Sponsor
Suggested answer: B
Explanation:

The implementation subject matter expert will be involved in the process to ensure that the requirements can be implemented.

Answer A is incorrect. The domain subject matter expert may be involved in the review and approval of requirements as defined by the stakeholder by the stakeholder roles and responsibility designation.

Answer C is incorrect. Project team members aren't involved in the decision of implementation, so this isn't a valid choice for this answer.

Answer D is incorrect. The project sponsor reviews the business case, solution, product scope, and all requirements and approves the documents before implementation.

asked 18/09/2024
Mohamed Ramez Hamad
38 questions

Question 132

Report Export Collapse

You are the business analyst for your organization and you're working to identify all of the stakeholders within your organization and outside your organization to ensure that you've captured the correct requirements for a project. Which one of the following techniques can be best suited for identifying stakeholders?

Interviews
Interviews
User stories
User stories
Acceptance and Evaluation Criteria
Acceptance and Evaluation Criteria
Risk analysis
Risk analysis
Suggested answer: A
Explanation:

An interview is a systematic approach. It is used for eliciting information from a person or a group of people in an informal or formal setting by talking to an interviewee, asking relevant Questions, and documenting the responses. Interviewees are also able to identify other stakeholders.

Answer C is incorrect. Acceptance and evaluation criteria are useful for identifying who has the authority to accept or reject solutions.

Answer D is incorrect. Risk analysis is the study of the probability, impact, and scoring of identified risk events. Risk analysis is the science of risks and their probability and evaluation in a business or a process. It is an important factor in security enhancement and prevention in a system. Risk analysis should be performed as part of the risk management process for each project. The outcome of the risk analysis would be the creation or review of the risk register to identify and quantify risk elements to the project and their potential impact.

Answer B is incorrect. User stories are useful to capture requirements, stakeholder attitudes, and for identifying actors and roles.

asked 18/09/2024
Fathy Refay
48 questions

Question 133

Report Export Collapse

When an organization implements a new solution, the organization will often have to provide dualsupport for the new solution and the solution that's being replaced. Which one of the following is not an input to the transitional requirements definition?

Stakeholder management strategy
Stakeholder management strategy
Deployed solution
Deployed solution
Stated requirement
Stated requirement
Organizational readiness assessment
Organizational readiness assessment
Suggested answer: A
Explanation:

There is not any stakeholder management strategy during the operational transfer. The correct answer is the organizational readiness assessment, the stated requirements, the deployed solution, and the designed solution.

Answer D is incorrect. The organizational readiness assessment is one of the four inputs to the definition transition requirements task.

Answer C is incorrect. The stated requirement is one of the four inputs to the definition transition requirements task.

Answer B is incorrect. The deployed solution is one of the four inputs to the definition transition requirements task.

asked 18/09/2024
Panayiotis Markatos
54 questions

Question 134

Report Export Collapse

The initial high-level listing of requirements in a change-driven approach is also known as what?

Requirements envisioning
Requirements envisioning
Requirements foundation
Requirements foundation
Product scope
Product scope
Project scope
Project scope
Suggested answer: A
Explanation:

The initial high-level listing of requirements in a change-driven approach is also known as requirements envisioning.

Answer D is incorrect. The project scope defines all of the required work to satisfy the requirements of the project.

Answer C is incorrect. The product scope defines all of the features and functions of the thing, solution, or service the project or organization will create.

Answer B is incorrect. Requirements foundation is not a valid term for business analysis.

asked 18/09/2024
tho nguyen
39 questions

Question 135

Report Export Collapse

Martha is the business analyst for her organization and she's been asked to help create a SMART goal for her company. Which one of the following organizational goals could be considered SMART?

No errors in production of customer products.
No errors in production of customer products.
Increase revenue by ten percent by January 15.
Increase revenue by ten percent by January 15.
Increase revenue by ten percent.
Increase revenue by ten percent.
Add 25 new customers to the sales base.
Add 25 new customers to the sales base.
Suggested answer: B
Explanation:

SMART means that the goals are specific, measurable, achievable, relevant, and time-bounded. The only goal that meets all of these requirements is the goal to increase revenue by ten percent by January 15.

Answer C is incorrect. This is not an example of a SMART goal because there is no deadline. Answer D is incorrect. This is not an example of a SMART goal because there is no deadline. Answer A is incorrect. This is not an example of a SMART goal because there is no deadline.

asked 18/09/2024
Mpho Ntshontsi
43 questions

Question 136

Report Export Collapse

There are four methods to generate a business need in an organization. Which approach would an organization use when there's recognized competition in the marketplace?

From the bottom up
From the bottom up
From external drivers
From external drivers
From middle management
From middle management
From the top down
From the top down
Suggested answer: B
Explanation:

From external drivers is used when there's recognized competition in the marketplace. Answer D is incorrect. From the top down is defined as the need to achieve a strategic goal.

Answer A is incorrect. From the bottom up is described as a problem with the current state of a process, function, or system.

Answer C is incorrect. From middle management is described as a manager needs additional information to make sound decisions or must perform additional functions to meet business objectives.

asked 18/09/2024
Kameron Katoku
50 questions

Question 137

Report Export Collapse

You are the business analyst for your organization. You are currently writing the business goals and objectives as part of the elements for the define business process. Which one of the following statements best describes the business goals and objectives element?

They describe all of the required work the project will need to complete in order to reach its objectives.
They describe all of the required work the project will need to complete in order to reach its objectives.
They describe the ends that the organization is seeking to achieve.
They describe the ends that the organization is seeking to achieve.
They describe the processes the solution will need to improve for the project to be successful.
They describe the processes the solution will need to improve for the project to be successful.
They describe all of the positive benefits in ratio to the risk and costs of the project.
They describe all of the positive benefits in ratio to the risk and costs of the project.
Suggested answer: B
Explanation:

Business goals and objectives clearly define the ends that the organization is seeking to achieve.

Answer C is incorrect. This is not a valid definition of the business goals and objectives.

Answer A is incorrect. This is a definition of the project scope.

Answer D is incorrect. This is not a valid definition of the business goals and objectives.

asked 18/09/2024
Cesar Augusto Veliz Reyes
52 questions

Question 138

Report Export Collapse

You are the business analyst for a large project for your organization. Your project has 65 stakeholders and this will greatly increase the complexity of the communication in this project. To demonstrate how complex this project and its communication will be, you show the management the number of communication channels in this project. How many channels exist in this project based on the number of stakeholders?

4160
4160
4225
4225
65
65
2080
2080
Suggested answer: D
Explanation:

There are 2,080 communication channels in this project. You can find the number of communication channels by using the formula N(N-1)/2 where N represents the number of stakeholders.

Answer B is incorrect. This is simply 65 times 65. Answer A is incorrect. This is simply 65 times 64.

Answer C is incorrect. This is the number of identified stakeholders.

asked 18/09/2024
Mareah Allawi
37 questions

Question 139

Report Export Collapse

In order to have high quality in requirements, all of the following characteristics should exist in the requirements except for which one?

Cohesive
Cohesive
Consistent
Consistent
Complete
Complete
Constrained
Constrained
Suggested answer: D
Explanation:

Constrained is not an attribute of high quality in a requirement. The requirements should be cohesive, complete, consistent, correct, modifiable, unambiguous, and testable.

Answer A is incorrect. Cohesive is one of the characteristics of quality in a requirement. Answer B is incorrect. Consistent is one of the characteristics of quality in a requirement. Answer C is incorrect.

Complete is one of the characteristics of quality in a requirement.

asked 18/09/2024
Kamal maru
45 questions

Question 140

Report Export Collapse

All of the following stakeholders participate in the prioritization of requirements except for which one?

Project team
Project team
Implementation subject matter expert
Implementation subject matter expert
Domain subject matter expert
Domain subject matter expert
Project manager
Project manager
Suggested answer: A
Explanation:

The project team does not participate in the prioritization of requirements.