Question 341

Report
Export
Collapse

A lead business analyst (BA) analyzed the performance of all BA's within the organization. How should the BA approach communicating the results to stakeholders?

Compare a solution used at another company
Compare a solution used at another company
Identify the performance objectives
Identify the performance objectives
Select performance measures
Select performance measures
Determine the reporting requirements
Determine the reporting requirements
Suggested answer: C
asked 18/09/2024
Joseph McCray
43 questions

Question 342

Report
Export
Collapse

A company wants to increase transaction service offerings using its on-line channels. The existing application already has some of the required functionality. A new project has been initiated to implement the additional capabilities but the company management is unsure of the complexity of the project. What exercise must be carried out to determine the changes needed in the new application?

Perform gap analysis of current and future states
Perform gap analysis of current and future states
Identify internal solution component dependencies
Identify internal solution component dependencies
Evaluate competitor applications
Evaluate competitor applications
Assess organizational culture
Assess organizational culture
Suggested answer: A

Explanation:

Gap analysis: A comparison of the current state and desired future state of an enterprise in order to identify differences that need to be addressed.

asked 18/09/2024
Farshin Golpad
38 questions

Question 343

Report
Export
Collapse

Stakeholders need a financial report that can be published and distributed to multiple end users.

They would also like the report to be developed within a specific time frame and within cost. What must the business analyst (BA) do to achieve this goal?

Review the project budget
Review the project budget
Revise business requirements
Revise business requirements
Define solution approaches
Define solution approaches
Update the project schedule
Update the project schedule
Suggested answer: A
asked 18/09/2024
Bruno Soriano
34 questions

Question 344

Report
Export
Collapse

A global organization is implementing a new Knowledge Management System and communication to the different regions has been informal. The approach is to convert the few remaining regions iteratively. The team has experienced variances at this point but feels confident in these final conversions. How should the business analyst (BA) communicate the information?

Repository
Repository
Document management
Document management
Email
Email
Individual collaboration
Individual collaboration
Suggested answer: A
asked 18/09/2024
Francis Arthur
37 questions

Question 345

Report
Export
Collapse

The business analyst (BA) has traced the requirements for the interaction between a customer and the new online ordering system. Besides enabling the BA to ensure quality of the requirements to stakeholders, tracing the requirements will also enable the BA to:

show all of the decision points in the business process.
show all of the decision points in the business process.
illustrate the relationships between relevant requirements.
illustrate the relationships between relevant requirements.
capture all users that will be impacted by the project.
capture all users that will be impacted by the project.
detail the inner workings of the system being changed.
detail the inner workings of the system being changed.
Suggested answer: B
asked 18/09/2024
Tristan Zerner
45 questions

Question 346

Report
Export
Collapse

A banking giant recently found a major security loophole in their online banking platform that could expose customer information. Security experts and the business analyst (BA) develop a low cost, low effort emergency fix to address this issue. What factor should the BA use to convince the bank to move forward with the emergency fix?

Cost
Cost
Schedule
Schedule
Impact
Impact
Urgency
Urgency
Suggested answer: D

Explanation:

The urgency of the repair is generally based on the level of disruption caused. In some cases the scope of the repair effort is very large, so the repair is managed as a project.

asked 18/09/2024
Reza Mirabrishami
39 questions

Question 347

Report
Export
Collapse

An organization's Business Analysis Center of Excellence (BACoE) has deployed several business analysts (BAs) to provide business analysis to a cross-functional initiative. After the first phase of the project, the BACoE seeks to determine the effectiveness of the business analysis work. Which of the following techniques could be used to elicit feedback from all affected stakeholders?

Brainstorming
Brainstorming
Business cases
Business cases
Surveys
Surveys
Root cause analysis
Root cause analysis
Suggested answer: C

Explanation:

Survey or experts (SMEs), whose responses are then collected and analyzed in order to formulate knowledge about the subject matter of interest. The Questions can be submitted in written form or can be administered in person, over the telephone, or using technology that can record responses.

asked 18/09/2024
Hicham Jellab
44 questions

Question 348

Report
Export
Collapse

An organization's Business Analysis Center of Excellence (BACoE) has deployed several business analysts (BAs) to provide business analysis to a cross-functional initiative. After the first phase of the project, the BACoE seeks to determine the effectiveness of the business analysis work. Which of the following techniques could be used to elicit feedback from all affected stakeholders?

Brainstorming
Brainstorming
Business cases
Business cases
Surveys
Surveys
Root cause analysis
Root cause analysis
Suggested answer: C

Explanation:

Survey or experts (SMEs), whose responses are then collected and analyzed in order to formulate knowledge about the subject matter of interest. The Questions can be submitted in written form or can be administered in person, over the telephone, or using technology that can record responses.

asked 18/09/2024
rafael Flores
52 questions

Question 349

Report
Export
Collapse

A project's business requirements require that the new solution reduce the labor costs currently attributed to performing end of month accounting procedures. Currently the company routinely must pay overtime to meet the deadline. The business analyst (BA) has been documenting the process and wants to ensure that the approach to the process design is feasible for the staff who perform the end of month procedures. Which of the following stakeholders will provide this verification?

Implementation subject matter expert
Implementation subject matter expert
Domain subject matter expert
Domain subject matter expert
Operational support
Operational support
Project sponsor
Project sponsor
Suggested answer: C
asked 18/09/2024
Laura G
57 questions

Question 350

Report
Export
Collapse

A business analyst (BA) is working on a set of tasks to establish a governance process for the project.

The BA intends to identify who has authority and responsibility to propose changes, who should be involved in the change discussions, and how changes will be documented and communicated. Which of the following are the inputs that would help the BA complete the task?

Business analysis approach and stakeholder engagement approach
Business analysis approach and stakeholder engagement approach
Governance approach and stakeholder engagement approach
Governance approach and stakeholder engagement approach
Governance approach and business analysis approach
Governance approach and business analysis approach
Stakeholder engagement approach and information management approach
Stakeholder engagement approach and information management approach
Suggested answer: A

Explanation:

Reference:

BABOK v.3.0 – IIBA – A Guide to the Business Analysis Body of Knowledge – International Institute of Business Analysis (2015) (Page 47)

asked 18/09/2024
Rocco Cristofaro
45 questions
Total 516 questions
Go to page: of 52
Search

Related questions