System designers are working with a business analyst (BA) during the initial stages of a project to implement a new transaction-based system. The system designers would like to have a visual that illustrates the type of information that will be input in the system, the processes it will support, and the location where it will be stored. What type of diagram meets the designers' needs?
A business analyst (BA) asked two stakeholders with approval authority to approve the requirements.
The stakeholders »re being asked to confirm that:
A business analyst (BA) has elicited the following requirement; "The solution must ensure the portal response times are under 2 seconds." What requirement classification schema does this requirement belong to?
A new product that is tablet-enabled is being considered to replace an older product to process orders. The data captured is sent to existing downstream applications which are not being updated.
What is the first thing that a business analyst (BA) should consider?
An organization has identified a market opportunity that could result in significant business gains. A business analyst (BA) is asked to assist in building the new business model. The BA begins by analyzing the current state. What input is critical to the current state analysis?
The claims intake workflow of an insurance company is being standardized across all branch offices.
The business analyst (BA) assigned to this project has interviewed users individually in all the offices and plans to schedule a workshop with all the users. What should the BA do to prepare for the workshop?
A business analyst (BA) held a formal walk through of requirements developed on a project.
Stakeholders expressed concerns because they had different interpretations of the requirements.
What activity would help ensure a common understanding?
A business analyst (BA) collected scanned notes, documents, and photos of whiteboards showing the results of a workshop pertaining to an accounting system replacement. What is the BA's next course of action?
A business analyst (BA) has set up a number of elicitation workshops with key subject matter experts (SMEs) on a new project. All SMEs have accepted the workshop invitations except for the legal SME who has not responded to any invitations. The first workshop is scheduled for next week and the BA has tried unsuccessfully to reach the legal SME by phone. How should the BA proceed?
A business analyst (BA) is developing requirements for a project with a limited budget. The business owner will be prioritizing requirements so that low value requirements can be de-scoped and the project remain within budget. Which of the following should the BA take into account to facilitate prioritization and ensure business objectives are met?