A business analyst (BA) spent three months eliciting, specifying, and modelling the detailed stakeholder and solution requirements. Right before requirement sign-off, the BA realized that the Vice President was unable to approve the requirements and the Chief Financial Officer should do so.

What element of requirement approval did the BA miss?

A.
Manage conflicts and issues
A.
Manage conflicts and issues
Answers
B.
Track and communicate approval
B.
Track and communicate approval
Answers
C.
Gain consensus
C.
Gain consensus
Answers
D.
Understand stakeholder roles
D.
Understand stakeholder roles
Answers
Suggested answer: D

An organization is planning to launch an exciting new service that has never been offered before. The expectations are that the service will be extremely popular with young families but, because the organization wants to keep it a secret until launch day. there is no way of knowing whether this is correct. Why does the business analyst (BA) suggest identifying high customer demand by young families as an "assumption?

A.
To assess the costs and benefits accurately
A.
To assess the costs and benefits accurately
Answers
B.
To prove the idea is correct
B.
To prove the idea is correct
Answers
C.
To manage the associated risks
C.
To manage the associated risks
Answers
D.
To provide a benchmark future change
D.
To provide a benchmark future change
Answers
Suggested answer: C

The business analyst (BA) has structured information so it is easy to find, does not conflict with other information, and is not duplicated unnecessarily. Which additional factor does the BA need to take into account when deciding how to structure the information?

A.
The level of experience with the repository tool
A.
The level of experience with the repository tool
Answers
B.
The number of stakeholders to be consulted
B.
The number of stakeholders to be consulted
Answers
C.
The size and complexity of the change
C.
The size and complexity of the change
Answers
D.
The governance and engagement approach to be used
D.
The governance and engagement approach to be used
Answers
Suggested answer: D

While planning the prioritization approach for an upgrade to a legal property application, the business analyst (BA) needs to check the organization's business policies prior to identifying the stakeholders to participate in the prioritization process. The business policies will help the BA because they:

A.
provide lessons learned from previous projects that should be incorporated into planning approach for current projects.
A.
provide lessons learned from previous projects that should be incorporated into planning approach for current projects.
Answers
B.
Outline the organizational roles and responsibilities in an effort to define a prioritization approach that involves the correct stakeholders.
B.
Outline the organizational roles and responsibilities in an effort to define a prioritization approach that involves the correct stakeholders.
Answers
C.
describe industry regulations and are used to develop a framework for sound business decision making.
C.
describe industry regulations and are used to develop a framework for sound business decision making.
Answers
D.
define the limits within which decisions must be made in accordance with contracts, agreement warranties or certifications.
D.
define the limits within which decisions must be made in accordance with contracts, agreement warranties or certifications.
Answers
Suggested answer: D

A business analyst (BA) is negotiating and resolving conflict with stakeholders to ensure they participate in the required BA activities. Which element of stakeholder management is the BA performing?

A.
Confirm elicitation results
A.
Confirm elicitation results
Answers
B.
Gain agreement on commitments
B.
Gain agreement on commitments
Answers
C.
Monitor stakeholder engagement
C.
Monitor stakeholder engagement
Answers
D.
Plan stakeholder engagement
D.
Plan stakeholder engagement
Answers
Suggested answer: D

A project manager asks a business analyst (BA) to conduct a meeting to walk the stakeholders through how requirements are structured. Which of the following requirement viewpoints will help the BA provide that information?

A.
State model
A.
State model
Answers
B.
Business capability analysis
B.
Business capability analysis
Answers
C.
Business process model
C.
Business process model
Answers
D.
Data streams
D.
Data streams
Answers
Suggested answer: C

A business analyst (BA) is preparing an analysis approach to replace a 12-year-old air traffic control system. The BA aims to define the solution definition before implementation, capture the information in standardized templates, and ensure that all activities are identified first and then divided into tasks. Which approach provides the appropriate level of formality for this project?

A.
Predictive
A.
Predictive
Answers
B.
Reactive
B.
Reactive
Answers
C.
Proactive
C.
Proactive
Answers
D.
Adaptive
D.
Adaptive
Answers
Suggested answer: A

A business analyst (BA) elicits requirements from end users for a new application, and then completes a set of use cases and use case scenarios. What should the BA do next?

A.
Identify all the roles and responsibilities
A.
Identify all the roles and responsibilities
Answers
B.
Review the use case scenarios
B.
Review the use case scenarios
Answers
C.
Conduct a requirements workshop
C.
Conduct a requirements workshop
Answers
D.
Create acceptance and evaluation
D.
Create acceptance and evaluation
Answers
Suggested answer: B

A business analyst (BA) has completed multiple workshops involving a number of stakeholders including the project manager however, the elicitation results are inconsistent between the stakeholders. How should the variation in results be resolved?

A.
The project manager should decide which requirement is relevant.
A.
The project manager should decide which requirement is relevant.
Answers
B.
The BA should select which requirements are correct.
B.
The BA should select which requirements are correct.
Answers
C.
The project manager should model requirements in a review meeting.
C.
The project manager should model requirements in a review meeting.
Answers
D.
The BA should model the elicited requirements in a review meeting.
D.
The BA should model the elicited requirements in a review meeting.
Answers
Suggested answer: D

A business analyst (BA) is working on a project to revise the way a company bills its customers. At the onset of the project, the BA creates the following matrix:

A.
Stakeholder analysis
A.
Stakeholder analysis
Answers
B.
Strategy analysis
B.
Strategy analysis
Answers
C.
Root cause analysis
C.
Root cause analysis
Answers
D.
Business capability analysis
D.
Business capability analysis
Answers
Suggested answer: A