A finance manager wants to begin a new project to replace the existing expenses processing system.
The finance manager feels that the current expense submission-to-reimbursement process takes too long and is substantiated by 50% more complaints regarding incorrect reimbursement amounts than the same time last year. What should the business analyst (BA) investigate first?
The following chart represents attendance of subject matter experts (SME) and the solution owner for a requirements review and approval meeting held weekly by a business analyst (BA).
The requirements package was approved by the solution owner during the May 30 meeting. After implementation of the solution, the BA learns that the users in SME-3 s area are not using the system. Which business analysis activity should the BA have monitored more closely to mitigate this situation?
The Chief Executive Officer (CEO) is concerned about how two client bases are going to be integrated and serviced in the newly formed company after a merger. A project has been initiated to implement a Customer Relationship Management (CRM) system for the new company that will contain the client information from both companies. What must the business analyst (BA) do to address the concerns of the CEO?
The Chief Information Officer (CIO) of a large financial services firm with many technology applications was formally reviewing all ongoing projects and noticed that the requirements were complex and difficult to follow. The CIO asks the business analyst (6A) what would improve the stakeholder's ability to understand the requirements. Which of the following will improve the requirements quality?
A project has experienced several schedule delays. A business analyst (BA) is assigned to the project to help get it back on track. The project manager believes that incomplete requirements are causing the missed milestones. What tool will help address the project manager's concern?
The product backlog refinement meeting for a project is complete but two stakeholders do not agree on the priority of several product backlog items. What should the business analyst (BA) do to help move the project forward?
A business owner has identified a high priority requirement that needs to be implemented immediately. The project manager has asked the business analyst (BA) to perform an impact analysis of this change. Which factor will the BA need to consider?
A business analyst (BA) is working on a project to improve product delivery. The issues arise during the latter stages of the delivery Freecycle and are due to poor communication of the business analysis information from the elicitation phase. As a result, a BA has ensured that the testing and training teams are identified as stakeholders on the RACI Matrix going forward. To which RAG designation should the training and testing teams be added?
A business analyst (BA) has spent the week conducting work sessions with a project's key stakeholders. Together, they have been reviewing user requirements and high-level design flowcharts to ensure that they have been correctly defined and documented. Which of the following describes the purpose of their work?
A change to support a regulatory requirement is proposed for inclusion in the scope of a project. A business analyst (BA) conducts an impact analysis to determine the extent of the change. What previous task could assist the BA in performing the impact analysis?