After an initial project kick-off meeting, the business analyst (BA) determined that the project has a short deadline and a regulatory mandate with stiff penalties for non-compliance. The stakeholders do not want to risk missing the deadline, and management is willing to commit any amount of resources to meet the deadline. Which kind of approach is suitable for the initiative?
A business analyst (BA) is planning how to present a set of requirements for a project with financial constraints. Which requirements attribute should the BA assign to allow cost implications to be assessed?
Several user groups are impacted by a proposed change to their daily work flow. How should the business analyst (BA) convey these changes so that the user groups understand the impact?
A business analyst (BA) has been asked to develop a plan to complete the associated business analysis activities for a project in which an organization is switching from a manual to an automated process for receiving payments. As the final step in developing the plan, which technique will the BA use?
A business analyst (BA) has been asked to develop a plan to complete the associated business analysis activities for a project in which an organization is switching from a manual to an automated process for receiving payments. As the final step in developing the plan, which technique will the BA use?
A certain stakeholder requirement has been analyzed and broken down into several solution requirements, each affecting a different IT system. After solution design, the business analyst (BA) receives feedback that one of the IT systems will take longer than anticipated to implement. What requirements artifact or technique will assist the BA in better understanding the related requirements?
A certain stakeholder requirement has been analyzed and broken down into several solution requirements, each affecting a different IT system. After solution design, the business analyst (BA) receives feedback that one of the IT systems will take longer than anticipated to implement. What requirements artifact or technique will assist the BA in better understanding the related requirements?
A business analyst (BA) identified that a stakeholder requirement for an online system led to a functional requirement to provide a user login screen. This is an example of which type of traceability relationship?
Two business analysts (BAs) are working on a requirement elicitation activity. One BA comes across a checklist that contains stakeholder details such as who are involved, location, group dynamics that are to be considered before beginning the elicitation activity and seeks a clarification from the second B
A system owner calls the project team to inquire about a recent change in one of the requirements, and insists that the change was never requested. What should the project team do to investigate the issue?