A domain subject matter expert (SME) describes a scenario to the business analyst (BA) that may need to be considered for an impending change. The BA and domain SME sketch out the process model for this exception scenario for consideration. What action does the BA take?

A.
Capture and integrate this process model into other appropriate planned outcomes
A.
Capture and integrate this process model into other appropriate planned outcomes
Answers
B.
Plan an observation activity to gain a hands-on understanding of the situation
B.
Plan an observation activity to gain a hands-on understanding of the situation
Answers
C.
Document the elicitation results then verify and validate in a requirements review
C.
Document the elicitation results then verify and validate in a requirements review
Answers
D.
Review the issue with stakeholders during a follow-up session
D.
Review the issue with stakeholders during a follow-up session
Answers
Suggested answer: C

A business analyst (BA) is working on a project that has a release date that cannot be changed. The BA engaged with stakeholders and completed the business requirements elicitation task. Upon review with the rest of the project team, it is determined that not all requirements can be implemented by the set deadline. What must the BA do to ensure maximum business value?

A.
Ensure test scenarios conform to business requirements
A.
Ensure test scenarios conform to business requirements
Answers
B.
Choose an appropriate format to communicate requirements
B.
Choose an appropriate format to communicate requirements
Answers
C.
Analyze requirements to remove unnecessary components
C.
Analyze requirements to remove unnecessary components
Answers
D.
Align business requirements to organizational strategy
D.
Align business requirements to organizational strategy
Answers
Suggested answer: C

Stakeholders initially agreed to an implementation schedule for a set of reports based on the value to business users. The development team provided a detailed estimate of the time required to develop each report based on the business requirements. What should the business analyst (BA) and the stakeholders do with the estimates?

A.
Revise the business requirements
A.
Revise the business requirements
Answers
B.
Write functional report specifications
B.
Write functional report specifications
Answers
C.
Review the priorities
C.
Review the priorities
Answers
D.
Analyze technical constraints
D.
Analyze technical constraints
Answers
Suggested answer: C

You are the business analyst for your organization and you're creating a data flow diagram to show how information is input, processed, stored, and output from a system. Which element of a data flow diagram represents a process that transforms data by combining it with other data?

A.
Data flow
A.
Data flow
Answers
B.
External entities
B.
External entities
Answers
C.
Data process
C.
Data process
Answers
D.
Concatenation
D.
Concatenation
Answers
Suggested answer: C

Explanation:

The data process describes the transformation of data in some way, either combining the data, reordering the data, converting the data, filtering the data, or other such activities.

Answer B is incorrect. An external entity is a source or destination of data. It is represented as a labeled rectangle.

Answer A is incorrect. Data flow identifies where data is being moved between a data process and an external entity, a data store or another data process.

Answer D is incorrect. Concatenation isn't a valid component of a data flow diagram so this choice is not valid.

You are a business analyst in an organization that has recently embraced business analysis as part of its initiative for new projects. In this organization, there is not an organizational standard for tailoring business analysis duties and expectations. Which one of the following best describes the action you should take to begin business analysis?

A.
Work with the appropriate stakeholders to determine how the business analysis work should be completed.
A.
Work with the appropriate stakeholders to determine how the business analysis work should be completed.
Answers
B.
Define the organizational standard first.
B.
Define the organizational standard first.
Answers
C.
Create a business case for the need of organizational standards for business analysis.
C.
Create a business case for the need of organizational standards for business analysis.
Answers
D.
Take charge and begin the business analysis activities, but document your approach to serve as a template for future business analysis initiatives.
D.
Take charge and begin the business analysis activities, but document your approach to serve as a template for future business analysis initiatives.
Answers
Suggested answer: A

Explanation:

The best answer is to work with stakeholders to determine what business analysis activities should be done in the present initiative.

Answer B is incorrect. There's not a need to define an organizational standard immediately, as this can evolve over time based on projects and business analysis experience in the organization.

Answer C is incorrect. A business case isn't needed; the business analyst needs to work with the stakeholders to define the needed activities.

Answer D is incorrect. While this answer is tempting, it does not address the cooperation and involvement of the stakeholders.

You are working with several business analysts to determine the solution approach for an identified problem. All of the following techniques are acceptable for identifying the solution approach except for which one?

A.
Benchmarking
A.
Benchmarking
Answers
B.
Brainstorming
B.
Brainstorming
Answers
C.
Decision analysis
C.
Decision analysis
Answers
D.
Risk analysis
D.
Risk analysis
Answers
Suggested answer: D

Explanation:

Risk analysis is not included as a technique for the solution approach. Risk analysis will be used later as part of the business case.