CompTIA PK0-005 Practice Test - Questions Answers, Page 13

List of questions
Question 121

Refer to exhibit.
Given the following network diagram:
Which of the following is the critical path?
Question 122

A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform first?
Question 123

A project team is defining operational training, discussing a go-live date, and describing the operational handoff. Which of the following best describes what the team is developing?
Question 124

Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?
Question 125

Which of the following is a reason to use a SOW on a project?
Question 126

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?
Question 127

Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?
Question 128

Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?
Question 129

During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?
Question 130

During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?
Question