Refer to exhibit.

Given the following network diagram:

Which of the following is the critical path?

A.
A-C-G-K-M
A.
A-C-G-K-M
Answers
B.
A-B-D-l-L-M
B.
A-B-D-l-L-M
Answers
C.
A-B-E-J-L-M
C.
A-B-E-J-L-M
Answers
D.
A-B-F-L-M
D.
A-B-F-L-M
Answers
Suggested answer: A

Explanation:

The critical path is the sequence of tasks that determines the minimum project duration. It is the longest path through the network diagram and has the least amount of slack or float.Based on the provided network diagram, the critical path is A-C-G-K-M, which has the longest total duration when adding up the individual task durations.Reference= The concept of the critical path is covered in the CompTIA Project+ Certification Study Guide1.For more detailed information on how to calculate and identify the critical path in project management, you can refer to the study guide and other project management resources2.

A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform first?

A.
Define the WBS.
A.
Define the WBS.
Answers
B.
Develop a RAM.
B.
Develop a RAM.
Answers
C.
Manage the vendors.
C.
Manage the vendors.
Answers
D.
Assess the resource pool.
D.
Assess the resource pool.
Answers
Suggested answer: D

Explanation:

This answer is based on the best practice of defining access requirements in project management, which is to identify the roles, responsibilities, and permissions of the project team members and other stakeholders who need to access the project information, resources, and deliverables12.The first step in this process is to assess the resource pool, which is the availability and capability of the human resources that can be assigned to the project34.By assessing the resource pool, the project manager can determine the skills, experience, and security clearance of the potential project team members, as well as their reporting relationships, communication preferences, and expectations56.This information can help the project manager to define the access requirements for each role and stakeholder group, and to assign the appropriate level of access to the project data, documents, tools, and systems78.Reference= CompTIA Project+ Certification Study Guide9, CompTIA Project+ Certification Exam Objectives10, What is Requirements Management?, How to Write Project Requirements, A Guide to Functional Requirements, Project Requirements Management: A Quick Guide, Creating clear project requirements, How to Define Project Roles and Responsibilities

A project team is defining operational training, discussing a go-live date, and describing the operational handoff. Which of the following best describes what the team is developing?

A.
The project closeout report
A.
The project closeout report
Answers
B.
A handover to operations
B.
A handover to operations
Answers
C.
Phase-gate review documentation
C.
Phase-gate review documentation
Answers
D.
A transition plan
D.
A transition plan
Answers
Suggested answer: D

Explanation:

A transition plan is a document that outlines how the project deliverables will be transferred to the operations team or the end users, and how the project team will disengage from the project. It typically includes details such as operational training, go-live date, support arrangements, roles and responsibilities, and acceptance criteria. A transition plan is different from a project closeout report, which summarizes the project performance, lessons learned, and final status. A handover to operations is a process of transferring the project deliverables to the operations team, but it is not a document. A phase-gate review documentation is a set of documents that are used to evaluate the project progress and readiness to move to the next phase, but it is not related to the operational handoff.Reference=CompTIA Project+ PK0-005 Certification Study Guide, Chapter 14: Closing the Project, p. 409-410; [CompTIA Project+ Certification Exam Objectives], Domain 4: Project Closure, Objective 4.1: Compare and contrast various project closure activities.

Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?

A.
The project manager did not release the resources.
A.
The project manager did not release the resources.
Answers
B.
The project is in the verification testing phase.
B.
The project is in the verification testing phase.
Answers
C.
The project manager did not complete the project closure phase.
C.
The project manager did not complete the project closure phase.
Answers
D.
The project manager did not remove access.
D.
The project manager did not remove access.
Answers
Suggested answer: C

Explanation:

If a project manager continues to receive project-related work after the project has been released into production, it suggests that the project closure phase was not completed properly. The project closure phase involves several activities, including ensuring that all project deliverables are accepted, documenting the lessons learned, releasing project resources, and formally closing the project. If these activities are not completed, the project can remain 'open' in a sense, leading to continued work and inquiries.

Reference= The answer is based on standard project management practices and the importance of the project closure phase as described in project management literature. For detailed information, please refer to the CompTIA Project+ Study Guide and other official CompTIA resources.Specific references to the closure phase can be found in the CompTIA Project+ PK0-005 Cert Guide1and the CompTIA Project+ Certification Exam Objectives2.

Which of the following is a reason to use a SOW on a project?

A.
To find out the contact information for the vendors
A.
To find out the contact information for the vendors
Answers
B.
To review the list of stakeholders
B.
To review the list of stakeholders
Answers
C.
To ensure the team stays within the scope of the contract
C.
To ensure the team stays within the scope of the contract
Answers
D.
To give explicit instruction on how to execute the work
D.
To give explicit instruction on how to execute the work
Answers
Suggested answer: C

Explanation:

A statement of work (SOW) is a formal document that defines the entire scope of work involved for a vendor and clarifies deliverables, costs, and timeline1.It serves as a contractual agreement between a vendor and a client, providing a comprehensive description of the work to be performed2.A reason to use a SOW on a project is to ensure the team stays within the scope of the contract, as it outlines what the team will and won't do on a project, saving from painful client negotiations and protecting the timeline and the bottom line3.Reference=CompTIA Project+ PK0-005 Certification Study Guide, Chapter 3: Initiating Projects Part 1, page 63;What Is a Statement of Work? Definition & Examples, Introduction and What Is a Statement of Work (SOW) In Project Management? sections;Statement Of Work Ultimate Guide: Simple Definition & Template, Introduction and What is a Statement of Work? sections;What Is a Statement of Work (SOW)? - Coursera, Introduction section.

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?

A.
Gantt chart
A.
Gantt chart
Answers
B.
Project organization chart
B.
Project organization chart
Answers
C.
Program Evaluation Review Technique chart
C.
Program Evaluation Review Technique chart
Answers
D.
Milestone chart
D.
Milestone chart
Answers
Suggested answer: D

Explanation:

A milestone chart is a tool that shows the key events or deliverables of a project along a timeline12.A milestone chart is useful for tracking the progress of a project that has technical tasks and requires a SME's knowledge, because it can provide a high-level overview of the project status, without getting into the details of each task or activity34.A milestone chart can help the PM and the project lead communicate the project achievements, challenges, and expectations to the stakeholders, and also identify any potential risks or delays that may affect the project completion56. A milestone chart is better than the other options because:

A Gantt chart is a tool that shows the tasks, dependencies, durations, and resources of a project along a timeline7.A Gantt chart is more detailed and complex than a milestone chart, and may not be suitable for providing high-level updates to the stakeholders8.

A project organization chart is a tool that shows the roles, responsibilities, and reporting relationships of the project team members and other stakeholders9.A project organization chart is not a tool for tracking project data, but rather for defining the project structure and authority10.

A Program Evaluation Review Technique (PERT) chart is a tool that shows the tasks, dependencies, and critical path of a project along a network diagram. A PERT chart is more focused on the sequence and timing of the project tasks, and may not capture the key milestones or deliverables of the project.

Reference= CompTIA Project+ Certification Study Guide, CompTIA Project+ Certification Exam Objectives, What is a Milestone Chart?1, How to Create a Milestone Chart in Excel in 3 Steps2, Milestone Chart: The Easiest Way to Track Project Milestones3, How to Use Milestones in Project Management4, What is a Gantt Chart?5, Gantt Chart vs Milestone Chart: What's the Difference?6, What is a Project Organization Chart?7, How to Create a Project Organization Chart8, What is a PERT Chart?9, PERT Chart vs Gantt Chart: What's the Difference?10

Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?

A.
Software as a service
A.
Software as a service
Answers
B.
Infrastructure as a service
B.
Infrastructure as a service
Answers
C.
Data as a service
C.
Data as a service
Answers
D.
Platform as a service
D.
Platform as a service
Answers
Suggested answer: B

Explanation:

Infrastructure as a service (IaaS) is a cloud model that provides on-demand access to cloud-hosted physical and virtual servers, storage, and networking resources. IaaS customers can provision, configure, and use these resources as they would use on-premises hardware, but without the hassle of purchasing, installing, managing, and maintaining them. The cloud service provider owns, manages, and maintains the hardware and computing resources in its own data centers, and charges the customers based on their usage. IaaS is suitable for customers who need flexibility, scalability, and control over their IT infrastructure, and who want to avoid the high costs and complexity of owning and operating their own hardware. The other options are not correct because:

Software as a service (SaaS) is a cloud model that provides on-demand access to ready-to-use, cloud-hosted application software. SaaS customers do not need to install, update, or maintain the software, as the cloud service provider handles all the technical aspects. SaaS is suitable for customers who need to access common applications, such as email, office productivity, or customer relationship management, without worrying about the underlying infrastructure or platform.

Data as a service (DaaS) is a cloud model that provides on-demand access to cloud-hosted data sources, such as databases, data warehouses, or data lakes. DaaS customers can query, analyze, and visualize the data, as well as integrate it with other applications or services, using APIs or web interfaces. DaaS is suitable for customers who need to leverage data from various sources, such as social media, IoT devices, or third-party providers, without having to store, manage, or process the data themselves.

Platform as a service (PaaS) is a cloud model that provides on-demand access to a complete, ready-to-use, cloud-hosted platform for developing, running, maintaining, and managing applications. PaaS customers can use the platform's tools, frameworks, libraries, and services to create and deploy applications, without having to worry about the underlying infrastructure or software. PaaS is suitable for customers who need to develop, test, and deploy applications quickly and efficiently, and who want to take advantage of the cloud's scalability, reliability, and security features.Reference=IaaS vs. PaaS vs. SaaS;AWS Fundamentals: Understanding Compute, Storage, Database, Networking & Security;What are the different types of cloud computing?;What is Cloud Storage and How to Use It

Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?

A.
Avoiding
A.
Avoiding
Answers
B.
Smoothing
B.
Smoothing
Answers
C.
Forcing
C.
Forcing
Answers
D.
Compromising
D.
Compromising
Answers
Suggested answer: A

Explanation:

Avoiding is a conflict resolution technique that involves postponing or withdrawing from a conflict situation. The project manager is using this technique by taking a break and continuing the meeting on another day, hoping that the conflict will resolve itself or become less important over time. This technique may be appropriate when the conflict is trivial, the potential damage is greater than the benefits, or more information is needed before making a decision.Reference=CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 10: Executing and Closing Projects, page 287; [CompTIA Project+ Certification Exam Objectives], Domain 3: Project Execution, Objective 3.2: Given a scenario, apply appropriate conflict resolution techniques.

During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?

A.
PERT chart
A.
PERT chart
Answers
B.
Milestone chart
B.
Milestone chart
Answers
C.
Gantt chart
C.
Gantt chart
Answers
D.
Budget burndown chart
D.
Budget burndown chart
Answers
Suggested answer: C

Explanation:

A Gantt chart is a visual tool used in project management to represent the timing of tasks required to complete a project. It is particularly useful for showing the start and finish dates of elements of a project, dependencies between tasks, and the current schedule status. This makes it an ideal choice for a project manager to discern overlapping tasks and allocate resources efficiently.

Reference= CompTIA Project+ Certification Study Guide (PK0-005)

During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?

A.
Schedule
A.
Schedule
Answers
B.
Status report
B.
Status report
Answers
C.
Issue log
C.
Issue log
Answers
D.
Task board
D.
Task board
Answers
Suggested answer: C

Explanation:

An issue log is a document that records and tracks any issues that arise during a project and how they are resolved1.It is different from a risk register, which records and tracks potential risks that may or may not occur during a project2. When a risk becomes an issue, it means that it has occurred and has a negative impact on the project.Therefore, the project manager should update the issue log next to document the compliance issue, its cause, its impact, its priority, its owner, and its resolution status3.Updating the issue log will help the project manager communicate the issue to the stakeholders, monitor the progress of the mitigation plan, and prevent similar issues from happening again4.Reference=CompTIA Project+ PK0-005 Certification Study Guide, Chapter 11: Executing Projects Part 2, page 331;Project Risk Mitigation Guide + Starter Kit | Smartsheet, Risk Register section;How to Make a Risk Management Plan (Template Included) - ProjectManager, Risk Register section;Issue Log - Project Management Knowledge, Introduction section;Issue Log Template: Free Download | ProjectManager, Introduction and How to Use an Issue Log sections.