CompTIA PK0-005 Practice Test - Questions Answers, Page 14

List of questions
Question 131

A piece of equipment has malfunctioned and is stalling the completion of a deliverable for a project. Which of the following should the project manager do next?
Question 132

A project team member wrote a user guide over the past ten days. Given the following scatter diagram.
Which erf the following can be formally conducted?
Question 133

Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite first?
Question 134

Which of the following metrics BE ST measures the alignment of the information security program to operational objectives?
Question 135

A project team is working on a document to precisely describe the success criteria that should be fulfilled by a product. Which of the following documents is the team preparing?
Question 136

A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps Which of the following actions should the project manager take?
Question 137

A project manager buys an extended warranty for a set of servers. Which of the following risk management strategies is the manager using?
Question 138

How does data discovery assist with data classification'?
Question 139

During a stand-up meeting, a team member asks to include a change that an important stakeholder requested in the project board. This request is denied, and the team member has to go back to what was originally planned for the sprint. Which of the following individuals should the stakeholder have asked to request the change instead of the team member?
Question 140

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?
Question