Question 1 / 40
Security software was accidentally uninstalled from all servers in the environment. After requesting the same version of the software be reinstalled, the security analyst learns that a change request will need to be filled out. Which of the following is the BEST reason to follow the change management process in this scenario?
Owners can be notified a change is being made and can monitor it for performance impact. Most Voted
A risk assessment can be performed to determine if the software is needed.
End users can be aware of the scope of the change.
A rollback plan can be implemented in case the software breaks an application.
Comment (0)
Suggested answer: A
Explanation:
change management process can help ensure that owners are notified of changes being made and can monitor them for performance impact (A). This can help prevent unexpected issues from arising.