ExamGecko
Home / IIBA / CCBA / List of questions
Ask Question

IIBA CCBA Practice Test - Questions Answers, Page 27

Question list
Search

List of questions

Search

Related questions











Question 261

Report
Export
Collapse

Complete this sentence. If a requirement cannot be verified, it cannot be successfully .

Scheduled
Scheduled
Estimated
Estimated
Assigned
Assigned
Implemented
Implemented
Suggested answer: D

Explanation:

Requirements must be verified in order to be implemented. If a requirement cannot be verified, it cannot be implemented, and therefore, does not meet a business need.

Answer B is incorrect. This is not the best answer for the Question. If a requirement cannot be verified, it cannot be successfully implemented.

Answer A is incorrect. If a requirement cannot be verified, it cannot be successfully implemented.

Answer C is incorrect. If a requirement cannot be verified, it cannot be successfully implemented.

asked 18/09/2024
Komalaharshini Basireddygari
42 questions

Question 262

Report
Export
Collapse

You are the business analyst for your organization and your manager has asked you to prepare an analysis of each proposed solution. Your manager wants you to determine whether and how each option can provide an expected business benefit to meet the stated business need. What is your manager asking you to create?

Feasibility study
Feasibility study
Abbreviated study
Abbreviated study
Alternative identification analysis
Alternative identification analysis
Quantified analysis
Quantified analysis
Suggested answer: A

Explanation:

Your manager is asking you to create feasibility study. This study reviews each solution to determine if the solution can meet the business benefit.

Answer B is incorrect. Abbreviated study is a form of feasibility analysis with a focus on changed initiatives with lower initiatives.

Answer C is incorrect. Alternative identification analysis isn't a legitimate business analysis term.

Answer D is incorrect. Quantified analysis is not a valid business analysis term to describe possible solutions for a business need.

asked 18/09/2024
Kanik Sachdeva
37 questions

Question 263

Report
Export
Collapse

You are the business analyst for your organization and you've been working with several stakeholders to gather requirements for approval.

The requirements have been approved with the exception of a conflict on one requirement. What must you and the stakeholders do in regard to this conflict before the business analysis endeavor may continue?

The requirement with the conflict should be excluded from the approved set of requirements and must be resolved before it can be joined to the approved set of requirements.
The requirement with the conflict should be excluded from the approved set of requirements and must be resolved before it can be joined to the approved set of requirements.
The conflict must be documented as a risk.
The conflict must be documented as a risk.
The conflict must be resolved before the set of requirements may be approved.
The conflict must be resolved before the set of requirements may be approved.
The conflict must be documented in an issues log, assigned to an issue owner, and then the endeavor may continue.
The conflict must be documented in an issues log, assigned to an issue owner, and then the endeavor may continue.
Suggested answer: C

Explanation:

Before the requirements can be approved, consensus must be reached among the stakeholders. The conflict must be resolved before moving forward in the endeavor.

Answer D is incorrect. This isn't a valid statement. Answer B is incorrect. This isn't a valid statement.

Answer A is incorrect. This isn't a valid statement.

asked 18/09/2024
Frantisek Kohanyi Kohanyi
37 questions

Question 264

Report
Export
Collapse

A business analyst wants to use benchmarking, but the project manager recommends against the approach. There are, as the project manager points out, several disadvantages to benchmarking.

Which one of the following is not a disadvantage to benchmarking?

Discovery of new approaches
Discovery of new approaches
Time consumption
Time consumption
Requirement of expertise of the person conducting the study
Requirement of expertise of the person conducting the study
Inability to produce innovative solutions
Inability to produce innovative solutions
Suggested answer: A

Explanation:

Benchmarking does allow for the discovery of new approaches that have worked elsewhere. Answer B is incorrect. Benchmarking can be time consuming.

Answer D is incorrect. Benchmarking can restrict new innovations, as the study is based on what's worked elsewhere.

Answer C is incorrect. Benchmarking does require expertise by the person completing the study.

asked 18/09/2024
Timothy Luisterburg
32 questions

Question 265

Report
Export
Collapse

Jason is creating a business case for his organization and management has asked him to assess the appropriate risks in the business case regarding the solution. Which one of the following risks is not a concern for Jason when defining the business case and associated risks?

Financial risk
Financial risk
Positive risk
Positive risk
Organizational risk
Organizational risk
Technical risk
Technical risk
Suggested answer: B

Explanation:

Positive risks are risks that may bring about a positive outcome if the event happens. This is not a concern for Jason in the initial risk assessment in the business case.

Answer D is incorrect. Technical risks evaluate whether the chosen technology and suppliers can deliver the required functionality.

Answer A is incorrect. Financial risks evaluate whether costs may exceed levels that make the solution viable or potential benefits may disappear.

Answer C is incorrect. Organizational risks determine whether the organization will make the changes necessary to benefit from the new solution.

asked 18/09/2024
Kumail Alsinan
41 questions

Question 266

Report
Export
Collapse

Which approach is best to take when a business analyst is assessing the solution options for a business need when there are relatively few criteria involved?

Focus on the life cycle costs of the solutions.
Focus on the life cycle costs of the solutions.
Focus on the commonalities of the solutions.
Focus on the commonalities of the solutions.
Focus on the differences of the solutions.
Focus on the differences of the solutions.
Focus on the implementation cost of the solutions.
Focus on the implementation cost of the solutions.
Suggested answer: C

Explanation:

When there are only few criteria involved, it's often easiest and most direct to focus on the differences of the solutions.

Answer B is incorrect. The commonalities of the solutions won't expose the weaknesses, strengths, and values between the solutions.

Answer A is incorrect. The life cycle costs may be considered, but there are other elements that can be considered too.

Answer D is incorrect. The implementation cost of the solution is usually considered, but it's the business value of the solutions that the business analyst should actually focus on.

asked 18/09/2024
Shameez Mohammed
37 questions

Question 267

Report
Export
Collapse

You are the business analyst for your organization and are working on organizing the identified requirements for a new solution. Nancy, your assistant in this process, says that these requirements aren't very complex. You agree but add that it's this thing that makes the overall solution complex.

What thing adds to the level of complexity among requirements?

Relationships among the requirements
Relationships among the requirements
Management in the project
Management in the project
Cost and schedule constraints
Cost and schedule constraints
Stakeholders in the project
Stakeholders in the project
Suggested answer: A

Explanation:

The relationships and inter-dependencies among the requirements add to the complexity of the requirements. Answer D is incorrect. Stakeholder management can be cumbersome, but the question was asking for a requirements characteristic, so this choice is incorrect.

Answer B is incorrect. Management in the project can add to the project complexity, but realistically management should stay out of the business analyst's duties. In addition, the question was asking about the complexity among the requirements.

Answer C is incorrect. Cost and schedule constraints deal more with the project implementation than with the identified requirements.

asked 18/09/2024
Melvin Bruijnaers
33 questions

Question 268

Report
Export
Collapse

What is the purpose of managing the solution scope and requirements from a business analyst's objective?

To complete business analysis activities as quickly as possible
To complete business analysis activities as quickly as possible
To obtain and maintain requirements approval from the sponsoring client about the solution scope
To obtain and maintain requirements approval from the sponsoring client about the solution scope
To obtain and maintain consensus among key stakeholders for the overall solution scope
To obtain and maintain consensus among key stakeholders for the overall solution scope
To complete business analysis activities as accurately as possible
To complete business analysis activities as accurately as possible
Suggested answer: C

Explanation:

The purpose of managing solution scope and requirements is to obtain and maintain consensus among key stakeholders regarding the overall solution scope and the requirements that will be implemented.

Answer A is incorrect. This isn't a valid answer, as the purpose of managing the solution scope and requirements is to gain consensus from the stakeholders, not to complete the business analysis tasks as quickly as possible.

Answer D is incorrect. This isn't a valid answer, as the purpose of managing the solution scope and requirements is to gain consensus from the stakeholders. While there's always a need for accuracy, this isn't the best answer for the Question.

Answer B is incorrect. This isn't a valid answer, as the purpose of managing the solution scope and requirements is to gain consensus from the stakeholders, not from the sponsoring client.

asked 18/09/2024
abdelhafid houssa
41 questions

Question 269

Report
Export
Collapse

You are a Business Analyst for your organization, and you're working with Mary. Mary wants to know what you need to complete the process of planning the business analysis approach if you're already the business analyst for your organization. Why is it important to complete the plan business analysis approach?

This task describes the amount of time needed for the business analysis approach.
This task describes the amount of time needed for the business analysis approach.
This task describes the amount of budget needed for the requirements elicitation.
This task describes the amount of budget needed for the requirements elicitation.
This task describes how to select an approach for performing business analysis.
This task describes how to select an approach for performing business analysis.
This task describes the processes the business analyst will or will not do based on the time and budget available.
This task describes the processes the business analyst will or will not do based on the time and budget available.
Suggested answer: C

Explanation:

The plan business analysis approach is required to select an approach that will perform business analysis. This approach helps to find out the following:

Which stakeholders need to be involved in the decision?

Who will be consulted regarding and informed of the approach? What is the rationale for using it?

Answer A is incorrect. This task does not address the schedule for the business analysis duties, just the approach the business analyst will be taking. While the task does describe when the tasks will take place, there's not an actual schedule coordinated at this point.

Answer B is incorrect. This task does not address the budget for the business analysis duties, just the approach the business analyst will be taking.

Answer D is incorrect. While this answer does address the business analysis approach, it doesn't qualify as there's not a schedule or budget consideration.

asked 18/09/2024
Shivanth Jha
34 questions

Question 270

Report
Export
Collapse

If an organization wants to re-use requirements, where should the defined requirements be kept?

Requirements management plan
Requirements management plan
Requirements repository
Requirements repository
Solution scope
Solution scope
Project management plan
Project management plan
Suggested answer: B

Explanation:

Requirements that are re-used in an organization are ideally kept in a requirements repository. One person should be identified to manage and control the repository.

Answer A is incorrect. Requirements for the current endeavor are kept in the requirements management plan, but not the set of requirements that will be reused.

Answer D is incorrect. The project management plan is not a valid answer, as this plan defines how the project will be planned, executed, monitored and controlled, and closed.

Answer C is incorrect. The solution scope is not a place where requirements that are reused will be kept and maintained.

asked 18/09/2024
Marco Romani
37 questions
Total 516 questions
Go to page: of 52