ExamGecko
Home / IIBA / CCBA / List of questions
Ask Question

IIBA CCBA Practice Test - Questions Answers, Page 17

List of questions

Question 161

Report Export Collapse

Which of the following defines all of the features and functions of the thing, solution, or service the project or organization will create?

Requirements envisioning
Requirements envisioning
Project scope
Project scope
Requirements foundation
Requirements foundation
Product scope
Product scope
Suggested answer: A, D
asked 18/09/2024
Jesus Ignacio Morales Vivancos
47 questions

Question 162

Report Export Collapse

You are the business analyst for your organization. You're considering if you should make a solution or purchase it from a vendor. If your team creates the solution, it will cost $286,000 and will cost $2,400 per month to support. The vendor's solution, however, will cost $239,000 and will cost $2,850 per month to support. How long will you need to use your in-house solution to be more cost effective than the vendor's proposed solution?

105 months
105 months
32 months
32 months
64 months
64 months
19 months
19 months
Suggested answer: A
Explanation:

In 105 months, your solution will equate to the cost savings offered by the vendor. In other words, if your solution will be kept longer than 105 months, it's best to use your solution. You can find this solution by first finding the difference of the build and buy costs, which is $47,000. Next, find the difference of the monthly costs, which is only $450. You'll then divide $47,000 by $450 for an answer of 104.4 months, or for this answer, 105 months.

Answer C is incorrect. 64 months is not the correct calculation to this scenario. Answer B is incorrect.

32 months is not the correct calculation to this scenario. Answer D is incorrect. 19 months is not the correct calculation to this scenario.

asked 18/09/2024
Edgar Alvarez
41 questions

Question 163

Report Export Collapse

You are the business analyst for your organization and you're notifying the key stakeholders of a need to gather requirements for an endeavor. One of the stakeholders that you'll need to attend your requirements workshop is the project manager. What role will the project manager have in this workshop?

The project manager will facilitate the requirements workshop.
The project manager will facilitate the requirements workshop.
The project manager will ensure that the needed resources are available.
The project manager will ensure that the needed resources are available.
None, the project manager should not be involved until all of the requirements have been identified.
None, the project manager should not be involved until all of the requirements have been identified.
The project manager will help elicit requirements from the stakeholders.
The project manager will help elicit requirements from the stakeholders.
Suggested answer: B
Explanation:

The role of the project manager in elicitation tasks is to ensure that the needed resources are available. Answer C is incorrect. The project manager will likely be involved in the requirements workshop.

Answer A is incorrect. The project manager won't facilitate the requirements workshop, the business analyst will.

Answer D is incorrect. The project manager may help elicit requirements from stakeholders, but this isn't the best choice for the Question.

asked 18/09/2024
Rik Ant
48 questions

Question 164

Report Export Collapse

You are a Business Analyst for your organization, and you're preparing to elicit requirements from stakeholders. You've gathered several inputs to help with the elicitation process. Which input will you use to ensure that you understand the type of information that should be elicited from stakeholders?

Roles and Responsibilities
Roles and Responsibilities
Stakeholder List
Stakeholder List
Business Need
Business Need
Risk Assessment
Risk Assessment
Suggested answer: C
Explanation:

The inputs required to prepare for elicitation are as follows:

Business Need. It guarantees that the type of information elicited from stakeholders is understood to the business analyst. This input is used at the time of eliciting business requirements.

Solution Scope and Business Case. It guarantees that the type of information elicited from stakeholders is understood to the business analyst. This input is used at the time of eliciting stakeholder, transaction requirement, and solution.

Stakeholder List, Roles, and Responsibilities. It is required for the identification of stakeholders that are required to participate in elicitation activity.

Answer D is incorrect. Risk Assessment is a review of the risks in the project, and isn't an input to the elicitation business analyst tasks.

asked 18/09/2024
Allen J Tyson
34 questions

Question 165

Report Export Collapse

Nancy has asked you to trace a particular requirement for her. What does 'to trace a requirement' mean?

Tracing a requirement means to look at a requirement and the others to which it is related. It links business requirements to components in the project's work breakdown structure.
Tracing a requirement means to look at a requirement and the others to which it is related. It links business requirements to components in the project's work breakdown structure.
Tracing a requirement means to track a requirement from its first identification all the way to its completion to see what issues, risks, costs, quality, and defects have surrounded the requirement.
Tracing a requirement means to track a requirement from its first identification all the way to its completion to see what issues, risks, costs, quality, and defects have surrounded the requirement.
Tracing a requirement means to look at a requirement and the others to which it is related. It links risk, cost, quality, and scope elements to stakeholder and solution requirements to other artifacts created by the team and to solution components.
Tracing a requirement means to look at a requirement and the others to which it is related. It links risk, cost, quality, and scope elements to stakeholder and solution requirements to other artifacts created by the team and to solution components.
Tracing a requirement means to look at a requirement and the others to which it is related. It links business requirements to stakeholder and solution requirements to other artifacts created by the team and to solution components.
Tracing a requirement means to look at a requirement and the others to which it is related. It links business requirements to stakeholder and solution requirements to other artifacts created by the team and to solution components.
Suggested answer: D
Explanation:

Tracing a requirement is the linkage of the requirements to all the parts of solution including its execution and creation.

Answer C is incorrect. This is not a valid definition of tracing a requirement. Requirement tracing does not consider risk, cost, quality, and other scope elements.

Answer A is incorrect. This is not a valid definition of tracing a requirement. It does not examine its position in the project WBS.

asked 18/09/2024
Nicolas Del Borrello
46 questions

Question 166

Report Export Collapse

Which elicitation activity is best described to ensure that the needed resources are organized and available for the elicitation?

Confirming elicitation results
Confirming elicitation results
Preparing for elicitation
Preparing for elicitation
Planning for elicitation
Planning for elicitation
Managing stakeholder requirements
Managing stakeholder requirements
Suggested answer: B
Explanation:

In order to conduct the elicitation process, the business analyst must work with the appropriate people, such as the project manager, to ensure that the needed resources are organized and available for the elicitation. Answer C is incorrect. Planning for elicitation is not a valid elicitation task.

Answer A is incorrect. Confirming elicitation results is the confirmation that the business analyst understands the requirements and that the stakeholder confirms the results of the elicitation.

Answer D is incorrect. Managing stakeholder requirements is not a valid elicitation task.

asked 18/09/2024
Arun Lailamony
46 questions

Question 167

Report Export Collapse

You are the business analyst for your organization. You're creating a document that states the business need, identifies the key stakeholders, and defines the positive impact the solution will bring to the organization and stakeholders. What document are you creating?

Requirements documentation
Requirements documentation
Business case
Business case
Project charter
Project charter
Vision statement
Vision statement
Suggested answer: D
Explanation:

This is an example of a vision statement. A vision statement, also called a problem statement, shows the categories of stakeholders and how the solution will help each stakeholder.

Answer C is incorrect. A project charter authorizes the project.

Answer B is incorrect. The business case justifies the cost of the solution for the rewards the solution will bring to the organization.

Answer A is incorrect. The requirements documentation doesn't define the benefits of the solution for the stakeholders; it only lists the requirements of the endeavor.

asked 18/09/2024
James Davis
46 questions

Question 168

Report Export Collapse

You are the business analyst for your organization. Management has asked you to create a plan that will define the proposed structure and schedule for communicating the business analysis activities to the appropriate stakeholders. What plan does management want you to create?

Stakeholder Management Plan
Stakeholder Management Plan
Business Analysis Plan
Business Analysis Plan
Communications management plan
Communications management plan
Business Analysis Communications Plan
Business Analysis Communications Plan
Suggested answer: D
Explanation:

Management is asking you to create the business analysis communication plan.

Answer C is incorrect. This is a specific question asking for the BABOK definition of the business analysis communication plan.

Answer B is incorrect. The business analysis plan defines the activities and scope of work.

Answer A is incorrect. The stakeholder management plan defines how the business analyst will manage the fears, threats, requirements, and demands of the stakeholders.

asked 18/09/2024
CHEUNG KA FAI
48 questions

Question 169

Report Export Collapse

Sam is the project manager of the NHT Project. His project has stakeholders from the end users, server administrators, functional managers, external customers, technicians, and executive managers. In this high- profile project, which group of stakeholders is the most important?

End users
End users
External customers
External customers
Executive management
Executive management
No stakeholders are more important than other stakeholders.
No stakeholders are more important than other stakeholders.
Suggested answer: B
Explanation:

Customers, internal or external, are always considered to be the most important group of stakeholders in a project. Recall that a stakeholder is anyone that has a vested interest in the outcome of your project.

asked 18/09/2024
Krishnan S Sridhar
39 questions

Question 170

Report Export Collapse

Which stakeholder map shows the relative influence, impact, and relation of stakeholders by plotting them closer to or farther away from the solution?

RACI Matrix
RACI Matrix
Onion diagram
Onion diagram
Control chart
Control chart
Tornado diagram
Tornado diagram
Suggested answer: B
Explanation:

An onion diagram shows the relative influence, impact, and relation of stakeholders by plotting them closer to or farther away from the solution. It is called an onion diagram because plotting of the stakeholders is done in ovals which, when completed, looks like an onion sliced in half.

Answer D is incorrect. A tornado diagram is often used to show opposing forces for a solution or issue. Answer A is incorrect. The RACI matrix explains the roles of the people involved in business analysis activities. It depicts stakeholders as having one or more of the following responsibilities for a given task or deliverable:

[R]. Responsible does the work [A]. Accountable is the decision maker (only one) [C]. Consulted must be consulted prior to the work and gives input. [I]. Informed means that they must be notified of the outcome

Answer C is incorrect. A control chart is a quality control tool that shows the results of measurements over time.

asked 18/09/2024
Beatriz Mejia
48 questions
Total 595 questions
Go to page: of 60
Search

Related questions