ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 764 - PMP discussion

Report
Export

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below.

What should the team do next?

A.
Ask the product owner if some low-priority stories could be cut from the sprint
Answers
A.
Ask the product owner if some low-priority stories could be cut from the sprint
B.
Continue with the sprint as the progress shows buffers for potential interruptions
Answers
B.
Continue with the sprint as the progress shows buffers for potential interruptions
C.
Ask the project team to select any additional stories as they have additional capacity than planned
Answers
C.
Ask the project team to select any additional stories as they have additional capacity than planned
D.
Continue with the sprint work as planned and keep monitoring
Answers
D.
Continue with the sprint work as planned and keep monitoring
Suggested answer: D
asked 23/09/2024
Wendie Canez
39 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first